Page 9 - Bernardon Proposal-Berwyn Fire Company Station 2
P. 9

www.bernardon.com













               Phase V – Construction Contract Administration          ■ After the General Contractor provides their
                                                                      record of completed punch list or incomplete or
               Once the Agreement with the single General Contractor   deficient items, we will review and supplement
               is executed, Bernardon will provide Construction       their punch list as necessary.
               Contract Administration services for the project.  At     ■ We will prepare and execute the Certificate of
               this time, we anticipate substantial completion of the   Substantial Completion and assist in the receipt
               building within fourteen (14) months of the General    of written warranties and project close-out
               Contractor’s Notice to Proceed.  During construction   documents.
               we will perform the following services:


                     ■ Bernardon will attend one (1) pre-construction   Optional Services
                    meeting and up to twenty-four (24) construction
                    progress meetings to observe the progress of
                    the work and to answer questions regarding the   Optional  Services  01:  Construction  Cost
                    construction.  The Structural Engineer will visit   Estimating
                    the site two (2) times.  The MPEFP Engineer will   In the event that BFC prefers to engage a cost
                    visit the site four (4) times including the punch   estimating  firm  to  provide  budgetary  estimates in
                    list visits.  We will prepare field reports following   lieu of Bernardon engaging a respected General
                    each visit to the site.                       Contractor, Bernardon will engage a construction cost
                     ■ On a monthly basis, we will review the General   consulting firm to provide a statement of probable
                    Contractor’s Application for Payment in the   construction cost at the conclusion of the Schematic
                    form of the AIA Document G702 for the scope   Design phase and Design Development phase for the
                    of completed work that is included as part of our   scope of architectural, structural, and MPEFP.
                    agreement.
                     ■ We will respond to the General Contractor’s
                    Requests for Information (RFIs) via written or   Optional  Services  02:  Exterior  Pad-Mounted
                    graphic means to interpret the intent of the   Emergency Generator
                    contract documents.                           Engineering services to perform emergency load
                     ■ We will provide shop drawing review of     calculations and to estimate emergency/standby
                    architectural, structural, and MPE components   generator size based on Owner’s/Client’s emergency
                    as required by the contract documents.  One   load requirements.  Provide designs for an exterior
                    (1) review of each required submittal plus    pad-mounted emergency generator, automatic
                    one (1) follow-up review is included provided   transfer switches, electrical single line riser diagram,
                    the submittal  is made in accordance with the   and specifications.  Excludes interior generator
                    contract documents.                           designs, ventilation systems, vent piping system, and
                                                                  combustion air which can be provided as additional
                                                                  services.







               BERNARDON | Proposal for Professional Design Services
               Berwyn Fire Company Station 2 | September 1, 2021                                               Page 7