Page 29 - Bernardon-Limestone Medical Center RFP Response
P. 29

www.bernardon.com













               Design Schedule


               Upon receiving Notice to Proceed, we will meet and collaborate with Limestone Medical Group, LLC, Aegis
               Property Group, and Project stakeholders to establish a mutually agreeable schedule that meets the goals of
               the project. Bernardon’s team of 78 professionals allows us to provide the necessary resources and support to
               complete the project in a timely manner; moreover, we have the flexibility to work with your team to modify
               our delivery schedule if the need should arise. The following project schedule outlines an approach that would
               lead to great success.


                    LIMESTONE MEDICAL CENTER                        July               August         September

                           MASTER PLANNING                      5-Jul  12-Jul  19-Jul  26-Jul  2-Aug  9-Aug  16-Aug  23-Aug  30-Aug  6-Sep  13-Sep  27-Sep

                 Project Schedule

                  1  Project Kick-Off & Existing Conditions Assessment
                                                              7/9
                  2  Existing Conditions Assessment
                                                              Week of 7/12/2021
                  3  Space Programming & Master Planning

                  a    Meet with LMC Leadership Team
                                                                  7/12
                  b    Develop a draft Space Program
                                                                          7/21-8/6
                  c    Review and Refine Space Program , as necessary
                                                                       7/19
                  d    Publish Final Approved Program
                                                                       7/21
                  e    Review and Refine Concepts, as necessary
                                                                     7/21 - 8/6
                  4  Provide Order of Magnitude Construction Cost Input
                                                                      Ongoing
                  5  Master Planning Report

                  a    Submit Draft Report
                                                                                           8/23
                  b    Review and Refine Draft Report
                                                                                              8/25 - 9/2
                  c    Submit Final Master Planning Report
                                                                                                  9/3
                  6  Budgeting and Project Scope Review
                                                                                                       9/4 - 9/30







            BERNARDON | Response to Request for Proposal Architectural and Engineering  Master Planning Services
            Aegis Property Group | Limestone Medical Center, LLC | July 1, 2021                           Page 22
   24   25   26   27   28   29   30   31   32   33   34