Nigeria has Supportive regulation for mini-grid

                                 developers



                                 Regulation for mini-grids in Nigeria are favorable to developers. In preparation for NEP, Nigeria

                                 has passed regulations that provide investors with certainty over future revenues/compensation


                                               Permitting                                         Tariff                              Grid Arrival Protection


                                  • For mini-grids below 100kW,                    • Tariff calculated using the                  • If a DISCO extends network to
                                     permitting process optional                      Multi Year Tariff Order (MYTO)                an isolated mini-grid, operator

                                      • Registration required                         Methodology designed for                      can either:
                                                                                      mini-grids                                      • Convert asset to an inter-
                                      • Developer relinquishes grid
                                         arrival protection                        • 15-year cost reflective tariff                      connected mini-grid
                                                                                      with limited yearly reviews                     • Transfer assets for
                                  • For isolated mini-grids over                      and major 5-year reviews                           compensation
                                     100kW, the permit application
                                     includes:                                     • Tariff set using building block              • No compensation applicable to
                                                                                      methodology                                   registered Mini-Grids
                                      • Community-developer
                                         agreement                                      • OPEX and overhead                       • In extension scenario,
                                      • NERC confirmation the mini-                     • CAPEX recoup over useful                  registered mini-grid needs to
                                         grid will not interfere with                      lives of assets                          decommission and relocate
                                         grid expansion                                 • Allowed return on capital                 within 2 months after
                                      • Written consent of local                           invested                                 commencement of grid supply
                                         DISCO (if mini-grid is in 5
                                         year expansion plan)
                                      • Proof area is unserved

                                      • Land acquisition/lease
                                      • Health and safety form

          01                          • E&S requirements