HSE IMPROVEMENTS


      HSE KAIZENS

      BEST 1 FROM FGD PROJECT RIHAND

                            BEFORE                                                      AFTER
              Elec Cables routed and dragged on ground             Proper cable routing above the ground is implemented





















      BEST 1 FROM FGD PROJECT MOUDA
                            BEFORE                                                      AFTER
                 Chances of fire during grinding work               Barrier divider provided to stop the spread of sparks





















      BEST 1 FROM FGD PROJECT FARAKKA

                            BEFORE                                                      AFTER
            No RCCB/ELCB provided for welding machines                    RCCB Installed to all welding machines