Page 5 - TOBIN Harbour Work
P. 5

THE WORK HAS BEEN DONE IN THREE DISTINCT ELEMENTS:


      1. Galway Harbour Inner Works
      This  involved  refurbishment  of  the  inner  harbour  including  quay  strengthening,  re-alignment  of
      docks, new support infrastructure, new inner dock marina.



      2. Galway Harbour Enterprise Park
      Commercial  activity  was  relocated  to  a  16  ha  site  adjacent  to  the  existing  waterfront.  Works
      undertaken by TOBIN included:
         Bridge Access
         Development of the Enterprise Park Including Civil and Structural Design
         Management of associated land transfers, site investigations, contract procurement and statutory

         Planning and EIA processes
         Project management of construction
         Consultation with all stakeholders and local interests



      3. Galway Harbour Extension
      This has involved feasibility studies, preliminary design, preparation of EIS and planning documents,
      consulting with An Board Pleanála to lodge as an SID project and assessment of possibilty of IROPI
      planning procedures Article 6(4).