Page 178 - ADMINISTRATIVE MANUAL
P. 178

159


 ACTIVITY   BY CONTRACT                    BY ADMINISTRATION

 OFFICE/UNIT   UNDERTAKING   OFFICE/UNIT                         UNDERTAKING
       Secures, if necessary, additional

       supporting documents from Univ.
       Infra Office and other Offices


       Submits to DBM request for
       release/s


       Follows up request/s when
       necessary


       Notifies the President upon

       release


       Pays 15% Mobilization Cost
 Pre-Completion   Central   except when not demanded by the  Executive Director   Pays Construction Materials/

 Payments   Administration   Contractor, or when the bidder is      Labor after delivery in
       the same Contractor who is                     accordance with existing COA
       working on the same Project or                 Rules and Regulations, and

       other Project/s within the same                the University Policy
       site (Campus). Pays periodically               Disbursement Scheme

       based percentage of
       Accomplishment                                 Pre-Audit Unit/Campus
                                                      Internal Auditor

       Prepares voucher with the
    Accounting   following signatories:

    Office   a.1 Letter a Univ. Director, Infra
       a.2 Chief Accountant
       a.3 President

       a.4 Preparation of check to be
       signed by the Cashier and

       countersigned by the President
       a.5 Cashier pays the Contractor


       Submits certification to the

    President through the VP.
   173   174   175   176   177   178   179   180   181   182   183