Page 110 - Updated SuDS Design & Evaluation Guide-Newham V3 Spreads
P. 110

Detailed Design  9.7.4 Dealing with spillage                   ■   ■  spillage is contained at or near the surface     9.7.5 Water quality design checklist                           Information presented for                     Detailed Design

           SuDS components are very effective at
                                                                     so that it is visible and accessible.
           dealing with ‘day to day’ pollution. When a
                                                                                                                              Item
                                                                                                                                                What is being checked
           spillage occurs this can overload the
                                                                                                                                                                                            assessment
                                                                     slow travel time through a SuDS
           treatment processes which occur within
                                                                     management train allows time for reaction
                                                                                                                              Method of
                                                                                                                                                                                            Design statement to specify method of
                                                                                                                                                Sensitivity of receptor and level of
           SuDS components.  Where the spillage is an
                                                                     and initial clean up to take place
                                                                                                                                                                                            discharge and sensitivity of receptor.
                                                                                                                                                treatment required
                                                                                                                              discharge
           organic based pollutant a spill kit is used to
                                                                     ■
                                                                     mechanical mechanisms such as shut off
           take up the excess and the residual pollutants
                                                                                                                                                site biodiversity and amenity assets and
           left in situ to breakdown naturally.
                                                                                                                                                                                            components and management train.
                                                                     valves should be avoided due to the
                                                                                                                                                the wider environment.
                                                                     inherent risk of the essential keys not be               Treatment         Sufficient treatment in place protecting    Layout drawing clearly indicating SuDS
                                                                                                                                                                                            Details of Indices approach and
           Designing for spillage should demonstrate:
                                                                     locatable at the time of spillage.  An                                     Evidence of source control, subcatchments  infiltration screening assessment (as
                                                                     awareness of outlet locations which are                                    and management train.                       appropriate).
                                                                     visible and can be easily sealed off will                Infiltration      Presence of SPZ’s, contaminated land,       Coordinated constraints plan. Evidence
                                                                     provide simple and robust containment.                                     depth to seasonal high groundwater table.  of discussion with EA where appropriate
                                                                                                                              Construction      Demonstration of how site runoff could be  Section of the drainage design
                                                                                                                              phase             managed during construction to minimise     statement outlining a potential approach
                                                                                                                                                the risk of pollution to the wider          for construction runoff management.
                                                                                                                                                environment due to silty construction       Contractors will be responsible for
                                                                                                                                                runoff.                                     uptake.
                                    Milk spillages will bypass conventional drainage methods of spill containment             Operation and  Operation and maintenance should be            Concise operation and maintenance
                                        https://naturalresources.wales/about-us/news-and-events/news/nrw-                     maintenance       simple to understand and easy to            plan. Description of tasks and detailing
                                                               respond-to-milk-spillage-in-llantrisant/?lang=en.              plan              implement. Where available, SuDS design     of where personnel are required to visit
  105                                                                                                                                           should deploy natural treatment process     site to remove hydrocarbon based              106
                                                                                                                                                to breakdown organic pollutants passively.  pollutants (i.e. organic pollutants have
                                                                                                                                                Contingency measures in the event of a      not been fully broken down passively as
                                                                                                                                                minor / major spillage                      part of SuDS treatment process).
                                                                                                                                                                                            Plan indicating potential for containment
                                                                                                                                                                                            and positioning of spill kits (as
                                                                                                                                                                                            appropriate)



























           Newham Council SuDS D & E Guide                                                                        © 2020 McCloy Consulting & Robert Bray Associates  Newham Council SuDS D & E Guide                                                                        © 2020 McCloy Consulting & Robert Bray Associates
   105   106   107   108   109   110   111   112   113   114   115