Page 92 - Updated SuDS Design & Evaluation Guide-Newham V3 Spreads
P. 92

Detailed Design  9.5.6  Managing runoff rates from                                                                                                                                                                                  Detailed Design

           Brownfield sites

           On Brownfield sites (also known as Previously
           Developed Land or PDL), if infiltration of the 1
           in 100 year rainfall event is not possible, the
           rate of discharge should be reduced to
           greenfield runoff rates. Where greenfield
           rates cannot be achieved, the designer must

           demonstrate why reduction in rate is not
           achievable. The designer will be required to
           demonstrate that they have explored all
           options for storage including the use of
           storage on roofs (e.g. blue-green roofs),
           permeable pavements, and the use of
           appropriately designed underground storage.
           (NSTS S3 and S6.)

           Not all planning applications comprise a
           complete redevelopment of the site, and only
           a small parcel of the overall site may be
           planned for re-development. On such
           occasions LLFA will not expect the entire
  87                                                                                                                                                                                                                                      88
           development to be returned to greenfield
           runoff status.

           In these circumstances LLFA will not accept

           the combining of the greenfield runoff rate
           for the development parcel with the existing
           impermeable runoff rate from the remainder                                                                                                                               Designers should provide the following:
           of the site when the designer is undertaking
           storage calculations.                                                                                                                                                       ■  the net increase in impermeable area

           The existing development remaining intact                                                                                                                                   ■  greenfield runoff rates are calculated
           and the parcel of land proposed for                                                                                                                                         based on the area of the redevelopment
           development should be treated separately in                                                                                                                                 parcel and not the wider development
           terms of calculations and drainage strategy.
                                                                                                                                                                                       ■  storage requirements for additional
                                                                                                                                                                                       impermeable area based on outflow
                                                                                                                                                                                       controlled to greenfield rates for the
                                                                                                                             Facing: The Islington, Ashby Grove Raingarden.
                                                                                                                             A raingarden for a single property with control           development parcel.
                                                                                                                             tube and overflow that can manage the 1 in 100
                                                                                                                             year return period rainfall event.


           Newham Council SuDS D & E Guide                                                                        © 2020 McCloy Consulting & Robert Bray Associates  Newham Council SuDS D & E Guide                                                                        © 2020 McCloy Consulting & Robert Bray Associates
   87   88   89   90   91   92   93   94   95   96   97