SCOPE AND ADMINISTRATION
[A] 109.3.6 Weather-exposed balcony and walking sur- [A] 110.2 Certificate issued. After the code official inspects
face waterproofing. Where the scope of work involves the building and does not find violations of the provisions of
balconies or other elevated walking surfaces exposed to this code or other laws that are enforced by the Department of
water from direct or blowing rain, snow or irrigation, and Building Safety, the code official shall issue a certificate of
the structural framing is protected by an impervious mois- occupancy that contains the following:
ture barrier, all elements of the impervious moisture bar- 1. The building permit number.
rier system shall not be concealed until inspected and
approved. 2. The address of the structure.
Exception: Where special inspections are provided in 3. The name and address of the owner or the owner’s
accordance with Section 1705.1.1, Item 3, of the Inter- authorized agent.
national Building Code. 4. A description of that portion of the structure for which
[A] 109.3.7 Fire and smoke-resistant penetrations. Pro- the certificate is issued.
tection of joints and penetrations in fire-resistance-rated 5. A statement that the described portion of the structure
assemblies, smoke barriers and smoke partitions shall not has been inspected for compliance with the require-
be concealed from view until inspected and approved. ments of this code for the occupancy and division of
[A] 109.3.8 Other inspections. In addition to the inspec- occupancy and the use for which the proposed occu-
tions specified in Sections 109.2 through 109.3.7, the code pancy is classified.
official is authorized to make or require other inspections 6. The name of the code official.
of any construction work to ascertain compliance with the
provisions of this code and other laws that are enforced by 7. The edition of the code under which the permit was
the Department of Building Safety. issued.
[A] 109.3.9 Special inspections. Special inspections shall 8. The use and occupancy in accordance with the provi-
be required in accordance with the International Building sions of the International Building Code.
Code. 9. The type of construction as defined in the Interna-
[A] 109.3.10 Final inspection. The final inspection shall tional Building Code.
be made after work required by the building permit is 10. The design occupant load and any impact the alter-
completed. ation has on the design occupant load of the area not
[A] 109.4 Inspection agencies. The code official is autho- within the scope of the work.
rized to accept reports of approved inspection agencies, pro- 11. If fire protection systems are provided, whether the
vided that such agencies satisfy the requirements as to fire protection systems are required.
qualifications and reliability.
12. Any special stipulations and conditions of the build-
[A] 109.5 Inspection requests. It shall be the duty of the ing permit.
holder of the building permit or their duly authorized agent to
notify the code official when work is ready for inspection. It [A] 110.3 Temporary occupancy. The code official is autho-
shall be the duty of the permit holder to provide access to and rized to issue a temporary certificate of occupancy before the
means for any inspections of such work that are required by completion of the entire work covered by the permit, pro-
this code. vided that such portion or portions shall be occupied safely.
The code official shall set a time period during which the
[A] 109.6 Approval required. Work shall not be done temporary certificate of occupancy is valid.
beyond the point indicated in each successive inspection
without first obtaining the approval of the code official. The [A] 110.4 Revocation. The code official is authorized to, in
code official, on notification, shall make the requested writing, suspend or revoke a certificate of occupancy or com-
inspections and shall either indicate the portion of the con- pletion issued under the provisions of this code wherever the
struction that is satisfactory as completed or shall notify the certificate is issued in error or on the basis of incorrect infor-
permit holder or an agent of the permit holder wherein the mation supplied, or where it is determined that the building or
same fails to comply with this code. Any portions that do not structure or portion thereof is in violation of any ordinance or
comply shall be corrected and such portion shall not be cov- regulation or any of the provisions of this code.
ered or concealed until authorized by the code official.
SECTION 111
SERVICE UTILITIES
SECTION 110
CERTIFICATE OF OCCUPANCY [A] 111.1 Connection of service utilities. A person shall not
make connections from a utility, source of energy, fuel, or
[A] 110.1 Change of occupancy. Altered areas of a building
and relocated buildings shall not be used or occupied, and power to any building or system that is regulated by this code
change of occupancy of a building or portion thereof shall not for which a permit is required, until approved by the code
be made until the code official has issued a certificate of official.
occupancy therefor as provided herein. Issuance of a certifi- [A] 111.2 Temporary connection. The code official shall
cate of occupancy shall not be construed as an approval of a have the authority to authorize the temporary connection of
violation of the provisions of this code or of other ordinances the building or system to the utility source of energy, fuel, or
of the jurisdiction. power.
8 2018 INTERNATIONAL EXISTING BUILDING CODE ®
Copyrighted © 2017 by, or licensed to, ICC (ALL RIGHTS RESERVED); licensed to UL, LLC pursuant to License Agreement with ICC. No further reproductions authorized or distribution authorized.
ANY UNAUTHROIZED REPRODUCTION OR DISTRIBUTION IS A VIOLATION OF THE FEDERAL COPYRIGHT ACT AND THE LICENSE AGREEMENT; AND SUBJECT TO CIVIL AND CRIMINAL PENALTIES THEREUNDER.