Page 12 - FSUOGM Week 31 2021
P. 12

FSUOGM                                PROJECTS & COMPANIES                                          FSUOGM


       Chevron gives update on Tengiz expansion





        KAZAKHSTAN       CHEVRON said in a July 30 update that the  Johnson, executive upstream vice president at
                         completion of the $45bn expansion of Kazakh-  Chevron, was set to say at a Q2 investor call on
      The expansion is aimed   stan's Tengiz oil field, the primary source for  July 30, according to a script released in advance.
      at lifting the field's   CPC crude blend, has been delayed until mid-  The WPMP component is set to be delayed
      production capacity to   2024 due to the COVID-19 pandemic.  to mid-2023 from late 2022 and the FGP com-
      850,000 barrels per   The expansion project is aimed at lifting the  ponent is delayed until around late 2023 and
      day.               field’s production capacity to 850,000 barrels per  mid-2024 from the original completion date of
                         day (b/d) of crude, or 1mn b/d of oil equivalent,  mid-2023.
                         which includes gas and gas liquids, and thereby   "Our cost target remains $45.2 billion as
                         give CPC volumes a major boost. Chevron  cost reduction efforts and favorable exchange
                         had already noted the likelihood of a delay to  rates offset an estimated $1.9 billion of incre-
                         the Future Growth Project (FGP) and Well-  mental costs associated with COVID," Johnson
                         head Pressure Management Project (WPMP).  was to say. "The COVID costs include mitiga-
                         The two sub-projects under the overall Tengiz  tion efforts, de-mobilization and remobili-
                         expansion would have involved deploying tens  zation costs, as well as the expected schedule
                         of thousands of workers to a remote site on the  extension.
                         eastern shores of the Caspian Sea along with a   "Although the total project cost target is
                         major logistical exercise for shipping modules  unchanged, we have increased the project con-
                         via the Russian canal system.        tingency to $1.9 billion, to recognize the sched-
                           "At FGP-WPMP overall progress is at 84%,  ule uncertainty associated with the virus and its
                         with field construction 69% complete. We've  variants. The project is currently at peak work-
                         recently reviewed our cost and schedule targets.  force and our primary focus is to mitigate the
                         At this point, the net schedule extension from  impact of the virus with vaccinations, testing,
                         the pandemic is expected to be roughly a quar-  and isolation protocols to enable workforce pro-
                         ter for WPMP and two quarters for FGP," Jay  ductivity." ™


       Caspian Sunrise shares surge after




       successful horizontal well




        KAZAKHSTAN       SHARES in Kazakhstan-focused junior Caspian  trading on July 27.
                         Sunrise surged on July 27 after the company   The BNG asset includes the shallow MJF
       The company has had   announced promising results from the first  structure, which is already in production, and
       setbacks at its deeper   horizontal well at its flagship BNG asset in the  deeper zones that Caspian Sunrise has been
       wells.            country’s west.                      test-flowing. The deeper drilling needed to tar-
                           The well was drilled into the MJF struc-  get these zones is costlier, but the rewards are
                         ture and yielded 645 barrels per day (bpd)  potentially much greater. But the company had
                         of crude over three days, Caspian said. At  suffered delays and technical setbacks at its deep
                         this rate, the company’s total output would  wells, and has therefore focused for the time
                         increase by around 50%. Oil from the well  being on maximising output from the shallow
                         will be sold at international rather than  wells.
                         domestic prices.                       Another difficulty for Caspian has been
                           Caspian plans to drill additional horizon-  the low payment it receives for domestic oil.
                         tal wells into the MJF structure and is awaiting  Obtaining export permits for oil is often a slow
                         a final licence upgrade at the South Yelemes  and arduous process for junior producers in
                         structure.                           Kazakhstan, where the government tries to keep
                           “For some time we have believed that the  some oil supply back for the domestic refining
                         shallow structure at the BNG contract area,  industry. These permits are sometimes granted
                         namely the MJF structure and the South  on a well-by-well basis.
                         Yelemes, would be suitable for a horizontal well,”   Until April, Caspian was receiving only $6
                         Caspian’s non-executive chairman, Clive Carver,  per barrel for oil sold domestically, although this
                         said in a statement. “The company now plans to  was then more than doubled to $12.4 per barrel.
                         drill further horizontal wells on each structure.”  But this still lags far behind international prices,
                           The news lifted Caspian’s share price by  with Brent currently trading at close to $75 per
                         19.15% to GBP0.028 in the first few hours of  barrel. ™




       P12                                      www. NEWSBASE .com                         Week 31   03•August•2021
   7   8   9   10   11   12   13   14   15   16   17