       Capacity to rise at South Azadegan





        IRAN             IRAN’S Petroleum Engineering and Develop-  PEDEC and the developers”. He added: “We
                         ment Co. (PEDEC) said this week that produc-  expect the development process of the South
                         tion capacity at the South Azadegan oilfield will  Azadegan joint field to be completed within a
                         increase by 15,000 barrels per day by the end of  year.”
                         next month.                            However, the timeline for completion is sev-
                           Speaking to the official Shana energy sector  eral months later than envisioned when a con-
                         media agency on the sidelines of the Ahvaz Oil  tract for the work was issued in July 2020.
                         Industry Exhibition, PEDEC CEO Abouzar   At that point, NIOC subsidiaries PEDEC and
                         Sharifi said: “By the end of the [current Iranian  Petropars signed a $1.26bn contract for the first
                         calendar] year, 15,000 barrels of oil will be added  development phase of the field. The upstream
                         to the production capacity of Azadegan South.”  portion of the contract includes drilling 35 wells,
                         The Iranian year 1401 ends on March 20.  installing 50 downhole ESP pumps and complet-
                           The latest update on the field’s capacity came  ing eight manifolds.
                         in June when Reza Dehghan said that it had   The midstream segment includes a 320,000-
                         reached 140,000 bpd with the North Azadegan  bpd central treatment export plant (CTEP),
                         asset understood to add another 75,000 bpd.  two intermediate separation plants, 328 km of
                           Sharifi added: “During the development  flow pipelines, 45 km of communication pipe-
                         activities, the exploitation of the parts that have  lines and 65 km of gas and crude oil transmis-
                         led to the production is also underway in the  sion pipelines running from the CTEP to the
                         first phase of [South Azadegan], and at the same  West Karun Pumping House and the NGL 3200
                         time, studies of the second phase development  facility. 10 of these wells were contracted to the
                         plan have started on the field.”     National Iranian Drilling Co. (NIDC), with
                           The field’s development project is seen pro-  Petropars awarding the final 25 wells to Dana
                         ducing 320,000 bpd in the first phase by the end  Energy and Tadbir Drilling Development Co. a
                         of the next Iranian calendar year.   month earlier.
                           The second phase is seen adding another   The expansion of South Azadegan, like the
                         280,000 bpd.                         other fields in the oil-rich West Karoun oil-
                           NIOC CEO Mohsen Khojastehmehr said  field cluster will play an important role in Iran
                         in January that “delays and shortcomings in  increasing its crude oil production capacity from
                         the development of these fields have been due  the current level of around 3.8mn bpd to 5.7mn
                         to defects in the contracts concluded between  bpd by the end of the decade.™