Page 9 - MEOG Week 39 2022
P. 9

MEOG                                 PRODUCTS & COMPANIES                                             MEOG


       TPAO presses forward with Sakarya




       ahead of first gas deliveries






        IRAN             STATE-OWNED Turkish Petroleum (TPAO)  during Q1 2023. Capital expenditure of around
                         continues to fast-track the development of the  $3.2bn is believed to be required to achieve first
                         offshore Sakarya gas field in the Black Sea, with  gas.
                         the company appearing set to feed first gas into   Speaking at the Grand National Assembly,
                         the Turkish grid on schedule.        BOTAS general manager Burhan Ozcan said:
                           The latest update came this week from Turk-  “We need to be ready systematically when our
                         ish Energy and Natural Resources Minister Fatih  Black Sea gas comes into operation in 2023.
                         Donmez, who was quoted by local daily Yeni  All infrastructure works related to this have
                         Shafak as saying following an inspection of facil-  been planned and investments have been initi-
                         ities that Sakarya gas will begin being delivered  ated,” Ozcan said at the Turkish Grand National
                         to consumers in March.               Assembly.
                           “We have 30 ships operating at sea. 140 km   He added: “The carrying capacity of our
                         of the 170 km [16-inch (406mm)] of pipeline  infrastructure will be 18-20 bcm per year […]
                         has been completed. 70% of the pipelines on  The day TPAO brings 40 mcm ashore, we will be
                         land have also been laid,” he said while visiting  in a position to carry it.”
                         Saipem’s Castorone pipelaying vessel. He added   Meanwhile, Erdogan added that output from
                         that around “32 km of the 10-inch [254mm]  Sakarya would ramp up to reach a peak output
                         pipeline, designed as an auxiliary line, have been  level of around 15 bcm per year in 2026, a year
                         completed, too”.                     later than previous guidance.
                           Casterone is installing the 165-km deep-wa-  TPAO has completed a 10-well drilling
                         ter section of pipeline, with Saipem’s Castoro  campaign to facilitate phase one production,
                         10 chosen to deploy 5 km of pipeline in shallow  but another 30 are planned to be drilled to ena-
                         water, which was completed in July.  ble peak output. To that end, TPAO recently
                           Donmez took to Twitter to say: “Sakarya gas  acquired a fourth drillship, and following main-
                         field will be the fastest offshore field develop-  tenance work this will join the Fatih, Kanuni and
                         ment project in the world, from exploration to  Yavuz vessels, which have all been deployed to
                         the first production.”               Sakarya. The new drillship – the Cobalt Explorer,
                           TPAO discovered 320bn cubic metres of gas  acquired from South Korea’s Daewoo Shipbuild-
                         at the Tuna-1 well in August 2020 and this was  ing & Marine Engineering (DSME) in Q4 last
                         subsequently upgraded to 405 bcm two months  year – has been renamed Abdulhamid Han.
                         later and renamed Sakarya. In June 2021, the   Donmez noted that its Oruc Reis seismic
                         company announced that it had found another  vessel, which had been operating in the Eastern
                         135 bcm with the Asmara-1 well, taking the total  Mediterranean, has been moved to Filyos for
                         volume discovered so far at Sakarya to 540 bcm.  maintenance.
                           The sections of pipeline will connect Sakarya   “The ship needed some modernisation work
                         to gas processing facilities under construction  related to hardware and software. [It] was previ-
                         at the port of Filyos in the northern province of  ously designed to conduct mostly 2-D seismic
                         Zonguldak.                           surveys. Now the ship becomes capable of per-
                           In June, Turkish President Recep Tayyip  forming 3-D seismic research, like the Barbaros
                         Erdogan said that the field’s first development  Hayrettin Pasha ship, and the assembly of the
                         phase would yield 10mn cubic metres per day  equipment is currently underway. We will com-
                         (3.65 bcm per year) of gas, which will begin  plete the modernisation work in a month and
                         being fed into the national transmission system  send it to the new location.”™






















       Week 39   28•September•2022              www. NEWSBASE .com                                              P9
   4   5   6   7   8   9   10   11   12   13   14