Page 5 - MEOG Week 38 2022
P. 5

MEOG                                         COMMENTARY                                               MEOG












































                           The field’s production plateau was previously  had happened at the facility’s surplus oil storage
                         revised downwards first from 1.8mn bpd to  system. It noted that loading and exporting from
                         1.2mn bpd and then to 800,000 bpd, though the  ABOT’s single-point moorings (SPMs) had not
                         timeline for the latest revision was also extended  been interrupted; rather that the interruption
                         from 2025 to 2030.                   had occurred at the main oil terminal.
                           A full 350,000 bpd addition to current out-  BOC added that loadings had “returned to
                         put levels will be achieved through the Yamama  their normal levels”, noting it would “compen-
                         expansion. This will account for a major part  sate for the pauses in the coming days by pump-
                         (more than 10%) of the country’s plans to  ing additional quantities, without affecting the
                         expand oil production capacity by 3mn bpd to  planned export rates”.
                         8mn bpd by 2027.                       The company concluded by saying that the
                           Lukoil holds a 75% stake in the WQ-2 TSC  spillage had been dealt with “in a record time
                         alongside the state-owned North Oil Co. This  not exceeding 24 hours”.
                         accords the developers a maximum remunera-  BOC has been working to rehabilitate two
                         tion fee of just $1.15 per barrel, and according  pipelines that feed the nearby Khor al-Amaya
                         to Wood Mackenzie, Lukoil’s net profit from  Oil Terminal (KAAOT). Ruptures in the con-
                         WQ-2 is just $0.56 per boe when considering  duits forced the terminal to go offline in 2017
                         state equity interest and tax, with this dropping  and only return to operations briefly in the inter-
                         to $0.19 per boe after applying the performance  vening period.
                         factor.                                A contractor has been hired to find and repair
                           Abdul Jabbar emphasised the need that  the fault, while a third pipe is to be installed, aim-
                         Lukoil maintain its efforts to increase production  ing to resume exports from KAAOT’s SPMs by
                         and expedite investment towards harnessing  the end of 2023. When operations resume, the
                         associated gas production. WQ-2 currently pro-  terminal is anticipated to operate at around
                         duces around 150mn cubic feet (4.25mn cubic  400,000 bpd, down from its 600,000 bpd capacity
                         metres) per day of associated gas.   prior to going offline.
                                                                In March, BOC said that the pipeline over-
                         Basra spill                          haul is part of efforts to increase crude export
                         The MoO released two other statements over  capacity from the southern ports to 6mn bpd by
                         the weekend, first announcing that an oil spill  2026. This will include the laying of two 48-inch
                         had occurred at the Al-Basrah Oil Terminal  (1,066-mm) pipelines as well as the construction
                         (ABOT) on September 15, then that it had been  and installation of new SPM facilities, with BOC
                         contained. The spill saw export capacity con-  preparing a tender worth around $1bn that will
                         strained by 1mn bpd, with Basra Oil Co. (BOC)  be opened up to international companies. Iraq’s
                         saying that its technical and engineering teams  current export capacity from its southern oil ter-
                         had worked swiftly to mitigate the spill, which  minals is around 3.4mn bpd.™



       Week 38   21•September•2022              www. NEWSBASE .com                                              P5
   1   2   3   4   5   6   7   8   9   10