Page 11 - DMEA Week 04 2021
P. 11

DMEA                                               LNG                                                DMEA












                                                                                                  LNG from the Virginia
                                                                                                  project will be used as
                                                                                                  trucking fuel.






























       Saipem enlisted for South




       African LNG FEED




        SOUTH AFRICA     ITALY’S Saipem has been enlisted to undertake   Meanwhile Canada’s Sproule will evaluate
                         front-end engineering design (FEED) work for  and certify Virginia’s second-phase reserves. It
                         the second phase of Renergen’s Virginia LNG  will base its estimates on additional data acquisi-
                         and helium project in South Africa.  tion and drilling work currently underway. The
                           Saipem will design facilities for producing  company bought MHA Petroleum Consultants
                         LNG and liquefied helium, including a gas  in 2019, which had previously been taking part
                         purification unit and a gas liquefaction unit  in the project.
                         that employs its own LiqueflexTM-N2 tech-  The three companies will present their stud-
                         nology. It will also draw up plans for product  ies in the second quarter of this year, after which
                         storage and offloading units and associated  Renergen expects to take a final investment deci-
                         utilities.                           sion (FID). Hiring the trio is a “significant step
                           Virginia will draw from gas fields across  forward in the planning of Phase 2, as it not only
                         Welkom, Virginia and Theunissen in South Afri-  defines the total capital expenditure required
                         ca’s Free State that contain very high quantities  but will clearly help define the project’s financial
                         of helium. Its first phase is due to start up later  parameters,” Renergen CEO Stefano Marani has
                         this year and produce at a rate of 350 kg per day  said.
                         of helium and 2,500 GJ of LNG. The helium will   Saipem’s XSIGHT unit will be working on the
                         be exported, while the LNG will be used domes-  Virginia facilities, with its upstream and LNG
                         tically, primarily for long-haul vehicle transport.  product manager saying the company’s technol-
                           The second stage will be “significantly more  ogies “for small to mid-scale natural gas liquefac-
                         substantial,” Renergen has said.     tion plants fully fit for this application, thanks to
                           The Johannesburg-based developer has also  their flexibility and robustness.”
                         hired South Africa’s EPCM Holdings for FEED   Renergen has struck deals with South Afri-
                         work on a gas gathering system for the second  ca’s Bulk Hauliers International Transport and
                         phase. The company is currently constructing  France’s Total on the supply of LNG from Vir-
                         the first-phase pipeline.            ginia for vehicle fuel. ™



       Week 04   28•January•2021                www. NEWSBASE .com                                             P11