Page 7 - AfrElec Week 03 2022
P. 7

AfrElec                                        NUCLEAR                                               AfrElec























































                         for Eskom’s plan to extend the lifespan of the  context of broader South African power strug-
                         power station by 20 years beyond its original  gles. The damages resulting from the Medupi
                         shutdown date in 2024.               Power Station explosion, which took out one of
                           “The durations for the less intensive outages  the plant’s generators, could take up to two years
                         have typically been between 35 and 50 days, and  to fix, said Yelland. While an extra unit may have
                         the more intrusive outages around 100 days in  come on at Kusile Power Station, it still needs to
                         duration,” said Phidza.              undergo testing and commissioning that will see
                           Once Unit 2 is back online, an outage of  it going on and off continually for the next six
                         a similar duration will follow for Unit 1. The  months to a year, he added.
                         extended unavailability of the units means that   “So, if you take all of this into account, my
                         the electricity supply system may be under addi-  analysis is that this year is going to be a more dif-
                         tional strain during the coming year, said Phidza.  ficult year than last year — and last year was a
                         He said that load shedding was not planned, as  record year for load shedding… and the previous
                         it was initiated only as a “last resort” to maintain  year was a record that was only beaten by 2021,”
                         the balance between generating capacity and  said Yelland.
                         demand.                                “I expect the energy availability factor of
                           Taking the two 920-MW units offline for a  Eskom to continue its slow decline.”
                         cumulative stint of about 10 months will leave   Phidza maintained that Koeberg’s units, as
                         South Africa with less power generation capacity  the largest generating units on the African conti-
                         than it would normally have, and thus increase  nent, provide a significant contribution to South
                         the risk of load shedding, according to Yelland.   Africa’s electricity demand.
                           “It all depends on how the rest of the plant   “The Koeberg Nuclear Power Station is an
                         performs, but there is no sign that the rest of the  important part of the Eskom generating fleet
                         plant is suddenly going to improve,” he said, add-  due to its reliable operation, low primary energy
                         ing that in the short term, the deep-level main-  costs, its strategic location in the Western Cape
                         tenance is likely to worsen the power generation  to stabilise the national electricity grid and
                         situation.                           the fact that it is a clean source of energy,” said
                           The outage also needs to be understood in the  Phidza.™



       Week 03   20•January•2022                www. NEWSBASE .com                                              P7
   2   3   4   5   6   7   8   9   10   11   12