MEOG NEWS IN BRIEF MEOG
to process and transfer maximum gas to SERVICES platform for the project of completion and
consumers; development of Forouzan Field, the last deck
Adopting policies to reduce energy Last deck of Forouzan (Heli Deck) of this platform weighing 142.6
intensity and optimize gas consumption in tons, was installed on the Roof floor. With
the domestic, commercial, administrative and platform installed this, installation of the decks of this platform
industrial sectors; with a weight of 1,300 tons was completed.
Developing infrastructure plans and The last deck (Heli Deck) of the FYA Completion of construction and
projects and pay serious attention to the residential platform of Forouzan Joint Field installation of the FYA residential platform
completion and timely delivery of current was installed in its designated offshore spot. with a capacity of 70 people will help to solve
projects. According to Iranian Offshore Oil the problem of housing the operational staff of
SHANA Company (IOOC), in continuation the Forouzan oil field.
of construction of the FYA residential SHANA