Page 8 - AsiaElec Week 33 2022
P. 8

AsiaElec                                              GRID                                           AsiaElec


       Pakistan seeks additional financing




       for “challenging” CASA-1000




        PAKISTAN          PAKISTAN’S National Transmission and Des-  financial management, disbursement, and
                          patch Company (NTDC) is reportedly seeking  reporting under the Projects; (iii) review the
                          additional financing of $35mn for additional  implementation status of the Converter Station
                          activities of the “challenging” Central Asia-South  and Electrode Station and line; (iv) get an update
                          Asian Electricity Transmission and Trade Project  on the implementation of the Resettlement
                          (CASA-1000).                         Action Plan (RAP); (v) Account bank procure-
                            The transmission project is to create condi-  ment; (vi) Technical code; and (vii) the project
                          tions for sustainable electricity trade between  restructuring process required from Pakistan.”
                          the Central Asian countries of Tajikistan and   NTDC, according to the newspaper, reported
                          Kyrgyzstan and the South Asian countries of  to the World Bank mission “that there was an
                          Afghanistan and Pakistan, but it has been hit by  incident on two towers on the CASA-1000
                          numerous delays and difficulties with the secu-  500kV HVDC Transmission Line, which is
                          rity situation in Afghanistan.       under construction and financed by Islamic
                            According to a cited aide memoire, the orig-  Development Bank (ISDB). The contractor of
                          inal cost of the project in Pakistan was $185mn,  the line had informed NTDC through a letter of
                          of which $92.66mn has already been disbursed,  June 27, 2022 which was forwarded to the Bank
                          whereas $46.74mn is to be released during the  on June 29, 2022 that on June 24, 2022, Towers #
                          current financial year. The closing date of project  184 and 185 of the 500kV HVDC Transmission
                          was to be extended by about three years from  Line were targeted by planting explosive mate-
                          March 31, 2023 to December 31, 2025.  rial on both towers. Tower #184 sustained severe
                            Business Recorder stated: “A World Bank  destruction, while the base of Tower #185 was
                          team led by Anthony Granville carried out the  partially damaged. NTDC security department
                          implementation mission from June 27 to July  along with Frontier Corps (FC) are currently
                          7, 2022 to review the implementation of the  investigating the incident and an updated report
                          project. The main objectives of the mission  along with a remedial measure to avoid such
                          were to: (i) discuss the implementation of the  incidents in the future would be forwarded to
                          CASA-1000 Project; (ii) review project status,  the Bank”.™
                          including procurement, contact management,












































       P8                                       www. NEWSBASE .com                         Week 33   17•August•2022
   3   4   5   6   7   8   9   10   11   12   13