       Kenya reports more delays for lake




       shipments of fuel to Uganda





        KENYA            KENYA Pipeline Co. (KPC) has said it does not  however, been impacted by the [coronavirus]
                         expect to begin deliveries of petroleum products  COVID-19 pandemic.” The KPC head did not
                         to Uganda via port facilities in Kisumu on sched-  say exactly when the Ugandan import facility
                         ule in January 2021.                 might be completed.
                           According to Irungu Macharia, the managing   He indicated, though, that the Entebbe jetty
                         director of the state-run fuel pipeline operator,  was expected to come online later in 2021.
                         the barge route across Lake Victoria will not   The route will not be able to handle regular
                         yet be ready to use by the target date because of  commercial shipments of fuel until it completes
                         problems in Uganda. Work on export facilities in  “several compliance processes” and gains access
                         Kisumu has proceeded as planned, he explained,  to a barge that can carry cargoes of up to 4.2mn
                         but operations at import facilities in Entebbe  litres across Lake Victoria, he added.
                         have fallen behind schedule.           Kenya and Uganda began working to estab-
                           “The Kisumu oil jetty has been delayed by the  lish an export corridor for petroleum products
                         delay in completion of complementary facilities  across Lake Victoria in 2013. They had initially
                         in Uganda,” Macharia was quoted as saying by  hoped to start using the Kisumu-Entebbe route
                         the Daily Nation. “The timing of the [Kisumu]  in 2019, but work has been delayed repeatedly.
                         jetty development was pegged on the construc-  KPC is already using a specialised ship to
                         tion of a jetty, vessels and receiving depot in  transport rail tankers full of fuel across the lake
                         Uganda by a private investor [Mhathi Infra, an  to destinations in Tanzania and Uganda. The
                         Indian company active in Uganda].    company conducted a dry-run test of this route
                           It was estimated that the works would be  last year, as well as a wet-run test that involved
                         completed by November 2020 and operations  the transfer of petroleum products from Kisumu
                         would commence by January 2021. This has,  to the Ugandan port of Jinja.™


                                             GAS-FIRED GENERATION

       Renergen completes design



       work for LNG plant





        SOUTH AFRICA      SOUTH Africa’s Renergen said last week that it   Once the gas liquefaction plant comes
                          had completed design work on its planned gas  online, Renergen will halt production of CNG
                          liquefaction plant 22 days ahead of schedule.  and switch to LNG. The company has already
                            In a statement, the company described the  arranged to work with a unit of France’s Total to
                          plant design as the fourth major milestone in its  promote the use of LNG as a fuel for long-haul
                          Virginia gas project. Achieving this goal is in line  trucking. Total will use its filling stations along
                          with efforts to launch LNG production in 2021,  the Johannesburg-Durban section of the N3
                          it said.                             highway to distribute LNG from the first phase
                            Renergen is building its LNG plant in two  of its South African partner’s plant.
                          stages. The first stage will involve connecting the   The second stage of Renergen’s LNG plant is
                          company’s natural gas wells near Welkom, Vir-  due to begin production in 2023. Part of the pro-
                          ginia and Theunissen in Free State to a new pipe-  duction from the second stage will distributed in
                          line. It will also encompass the construction of  Total retail outlets along all South Africa’s major
                          the gas liquefaction plant and of a helium plant.  highways, and the remaining volumes will be
                            The latter facility will take advantage of the  sold to other buyers.
                          fact that Renergen’s gas fields contain an unu-  Renergen recently held South Africa’s first
                          sually high concentration of helium. Sproule,  LNG auctions. It announced the start of the sales
                          an international energy consulting firm, has  on July 20, saying it would accept offers for future
                          estimated that they may hold as much as 9.74bn  production streams of LNG and helium from its
                          cubic metres of helium, a quantity that exceeds  plant until August 28.™
                          the total proven reserves of North America.