Page 5 - MEOG Week 04 2021
P. 5

MEOG                                         COMMENTARY                                               MEOG


                                                                                                  Saudi Aramco’s pipeline
                                                                                                  network.

                                                                                                  Source: IPO prospectus
































                         Bid delays                           cancelled its tender for engineering, procure-
                         Given these challenging financial headwinds  ment and construction (EPC) maintenance
                         facing Aramco and following Crown Prince  work at Marjan with a separate contract for a
                         Mohammed bin Salman’s decision to cut output  tie-in platform and two production deck mod-
                         by 1mn bpd during each of February and March,  ules at the field also written off.
                         it should come as little surprise that the company   Saudi oil production has been mandated at
                         is set to extend delays to highly-anticipated ten-  just over 8mn bpd for the next two months, a
                         dering processes under the long-term agreement  level that gives it a spare sustainable capacity of
                         (LTA) programme.                     3mn bpd.
                           The bidding deadline for contract release   With Aramco still smarting from the events
                         purchase orders (CRPOs) 62, 63, 64 and 65 is  that caused it to cut its 2020 capital programme
                         understood to be set for a delay until April at the  by around $12bn, there is little urgency in Dhah-
                         earliest while several contracts announced in  ran to commit to more spending.
                         2020 are yet to be formalised.         This hesitation will of course subside as the
                           As part of wide-ranging efforts to minimise  company follows through on the Ministry of
                         the business impact of COVID-19, Aramco  Energy’s directive to increase maximum sustain-
                         delayed by six months the Marjan and Berri  able capacity (MSC) from 12mn bpd to 13mn
                         crude increment programmes during Q2 2020;  bpd, though in the short-term, Aramco’s LTA
                         projects that are set to more than double oil pro-  contract tenders, which have long provided shel-
                         duction capacity from the assets to a combined  ter from oil price storms to those lucky enough
                         1.35mn bpd at a cost of around $18bn. These  to be prequalified, are likely to focus on smaller
                         developments are also expected to result in the  jobs rather than the multi-billion-dollar sort that
                         production of up to 2.5bcf (71mcm) per day of  have grabbed so many headlines in the past.
                         associated gas, which will be piped to the Berri   As Aramco focuses on maintenance and
                         gas plant.                           issues of urgent need, its major increment pro-
                           In August, Aramco  is  reported to have  grammes will remain on the back burner.™




















       Week 04   27•January•2021                www. NEWSBASE .com                                              P5
   1   2   3   4   5   6   7   8   9   10