       IDC begins Majnoon drill work,




       drive towards 450,000 bpd




        IRAQ             THE state-owned Iraqi Drilling Co. (IDC) this  reasons. The two companies had signed a techni-
                         week reported that it had begun drilling the first  cal services contract (TSC) for the field following
                         of a 43-well drilling campaign at the supergiant  the second licensing round in 2009.
                         Majnoon oilfield as the field’s operator looks to   This paid a maximum remuneration fee
                         ramp up output.                      of $1.39 per barrel, setting an ambitious pla-
                           A statement from the Ministry of Oil (MoO)  teau production target of 1.8mn bpd, which is
                         seen by NewsBase said that IDC’s technical and  unlikely ever to be reached.
                         engineering staff had begun drilling the MJ-129   Abdul Jabbar lauded BOC for reducing costs
                         well on behalf of Iraqi National Oil Co. (INOC)  associated with the field by 30% during the
                         subsidiary Basra Oil Co. (BOC) in the southern  three and a half years it has been in charge of
                         Basra Governorate.                   proceedings.
                           IDC director-general Basem Abdul Karim   In July, BOC and its engineering, procure-
                         was quoted as saying that the work followed  ment and construction management (EPCM)
                         completion of “all the necessary preparations  lead on Majnoon field development, KBR,
                         for preparing and operating the drilling rig  awarded a contract to UK-based Proserv Con-
                         equipment”.                          trols to manufacture and deliver 22 wellhead
                           He said that the well would be drilled to a total  control panels (WHCPs) for use in the field.
                         depth of 3,648 metres using the IDC 56 drilling   Each of these can control up to four wells at
                         rig to target the productive Mishrif formation.  once and BOC intends to employ the units on 70
                           The start of drilling follows the announce-  new wells that continue to be drilled.
                         ment in December by Oil Minister Ihsan Abdul   Proserv has begun drilling the WHCPs and
                         Jabbar of a production capacity target of 450,000  expects to complete the contract by the end of
                         barrels per day, up from the current 240,000 bpd.  Q1 2022.
                           With reserves of nearly 13bn barrels and far   Majnoon is one of many fields targeted for
                         higher resources, Majnoon, whose name trans-  a major capacity increase by the MoO, which
                         lates as ‘insane’, is one of Iraq’s largest assets, but  is working to expand nationwide production
                         has so far failed to fulfil much of its potential.  capacity from 5mn bpd to 8mn bpd by 2027.
                           BOC assumed operatorship of the field in   IDC has announced the start of drilling cam-
                         2018 after the departure of Shell and Malaysia’s  paigns across the country, including at Khabbaz
                         Petronas the previous year, with reservoir pres-  in Kirkuk Governorate, Amarah and Buzurgan
                         sure concerns and corruption cited as potential  in Missan Governorate and Zubair in Basra.™