Page 11 - GLNG Week 11 2022
P. 11

GLNG                                              ASIA                                                GLNG


       Sri Lanka’s Supreme Court dismisses legal




       challenge against LNG-to-power project




        PROJECTS &       SRI Lanka’s Supreme Court on March 4 dis-  the coast of Colombo. Under the terms of the
        COMPANIES        missed a legal challenge against a proposed  agreement, the company would have gas supply
                         LNG-to-power project that is being developed  rights to the Kerawalapitya power complex and
                         by New Fortress Energy (NFE). The company  would initially provide Sri Lanka with an esti-
                         subsequently reiterated its commitment to the  mated 1.2mn (4.5mn litres) gallons per day of
                         project in a March 8 statement.      LNG. This would be used to supply both the cur-
                           “Having considered the merits of all the fun-  rently operational 310-MW Yugadanavi power
                         damental rights petitions filed seeking to halt  plant and the 350-MW Sobadanavi power plant,
                         NFE’s development of natural gas power solu-  which is due to enter service in 2023.
                         tions in Sri Lanka, the court fully dismissed the   Sri Lanka’s government has long been calling
                         petitions without further hearing,” NFE said.  for gas to make up at least one-third of the coun-
                           “We are pleased that the court has dismissed  try’s energy mix by 2030, up from zero today.
                         these petitions, as NFE can now proceed with  However, despite the government also trying to
                         our plans to deliver cleaner fuels and more relia-  revive interest in developing untapped offshore
                         ble, affordable power to Sri Lanka,” stated NFE’s  gas deposits, the only way of adding gas to Sri
                         chairman and CEO, Wes Edens.         Lanka’s energy mix currently is via the import of
                           According to the statement, the company  LNG. Various plans to import LNG have failed
                         struck a definitive agreement with the govern-  to gain traction in recent years, with complex
                         ment of Sri Lanka in September 2021, paving  bureaucracy and political volatility acting as
                         the way for NFE to build an LNG terminal off   roadblocks to new projects.™





       McDermott completes subsea work at




       Bayu-Undan as Santos kicks off CCS FEED





        PROJECTS &       MCDERMOTT International announced on  execution of its contract. Recovery and reuse of
        COMPANIES        March 10 that it had completed subsea work  existing flowlines was a “significant factor” in
                         under its engineering, procurement, construc-  enabling the work to be completed on schedule,
                         tion and installation (EPCI) contract, awarded  within nine months of being awarded the con-
                         by Australia’s Santos for the Bayu-Undan  tract, it added.
                         project.                               Meanwhile, Santos has entered the front-
                           The Bayu-Undan field is one of Timor-  end engineering and design (FEED) phase of
                         Leste’s largest gas fields, located in the Timor Sea  a proposed carbon capture and storage (CCS)
                         around 200 km off the country’s south-east coast  project at Bayu-Undan. The project would have
       Bayu-Undan provides   and roughly 500 km off the north-west coast of  the capacity to store up to 10mn tonnes per year
       feedstock gas to the   Darwin, Australia. It supplies feedstock gas to  (tpy) of carbon dioxide (CO2) and would also
       Darwin LNG project in   the Darwin LNG terminal, which is also oper-  serve Darwin LNG.
       Australia.        ated by Santos.                        Santos said in a March 9 statement that the
                           The work McDermott was carrying out was  FEED work would include engineering and
                         for the infill well Phase 3C project at the field.  design for additional CO2 processing capacity
                         Work on Phase 3C began in May 2021 and ended  at Darwin LNG as well as the repurposing of the
                         in December, McDermott said. The company’s  Bayu-Undan facilities for carbon sequestration
                         scope of work involved the tieback of a single  operations after gas production from the field
                         in-field well to existing facilities, re-using exist-  ends.
                         ing flexible flowline, with a new umbilical and   The company believes the CCS project has
                         certain infrastructure.              the potential to be one of the largest in the world,
                           McDermott said recovery of existing flexible  and has talked up the scheme’s potential to cre-
                         flowlines, flushing to clear hydrocarbons, re-lay-  ate jobs and provide a new revenue stream for
                         ing and a tieback from a new in-field well to the  Timor-Leste once Bayu-Undan is no longer pro-
                         existing Bayu-Undan facility were all key to the  ducing gas.™



       Week 11   18•March•2022                  www. NEWSBASE .com                                             P11
   6   7   8   9   10   11   12   13   14   15   16