       TAP asks for more time to launch




       gas flows to Italy




        ITALY            ITALIAN regulators have granted the develop-  South Caucasus Pipeline Expansion (SCPX) and
                         ers of the Trans-Adriatic Pipeline (TAP) until  the Trans-Anatolian Pipeline (TANAP), were
       TAP says gas flows will   December 2021 to launch gas flows from Azer-  brought on stream in 2018, enabling Turkey to
       start by the end of this   baijan to Italy, the project’s consortium told Platts  ramp up purchases of Azeri gas.
       year, but it has asked   on July 2, while insisting its goal is still to start   TAP, which runs from western Turkey
       the regulator for until   supplies in the fourth quarter of this year.  through Greece, Albania, and under the Adriatic
       December 2021 to    “The TAP project is more than 96% complete  Sea to Italy, had been expected to start pumping
       reach that step.  and reconfirms the target of transporting first gas  gas in mid-2020. But its launch was later pushed
                         to Europe [in] 2020," a group spokesman told  back to October this year, reportedly because of
                         Platts. But he said the consortium had neverthe-  environmental opposition to construction in
                         less asked for more time from regulators, in case  Italy.
                         of further obstacles beyond its control.  “The project has faced several major
                           TAP, whose shareholders include BP (20%),  impacts, beyond its control, mainly with ref-
                         Azerbaijan’s SOCAR (20%), Italy’s Snam (20%),  erence to permitting/regulatory obstacles, sev-
                         Belgium’s Fluxys (19%), Spain’s Enagas (16%)  eral safety and security breaches, suspension
                         and Switzerland’s Axpo (5%), secured an exemp-  of construction activity due to multiple legal
                         tion from certain European provisions in 2013.  proceedings, unforeseen geotechnical/natural
                         This was conditional on the pipeline becoming  events, as well as the wide-ranging effects of the
                         operational within six years, or by June 2019.  [coronavirus] COVID-19 pandemic and other
                         TAP obtained in 2014 a first extension until  factors mentioned above,” TAP told Platts.
                         December 2020, and has now received a second  “TAP will endeavour to commence first gas
                         until December 2021.                 deliveries by the end of the year. Nonetheless,
                           TAP forms the third and final section of the  should the effects of the COVID-19 pandemic
                         Southern Gas Corridor (SGC), a $40bn net-  persist, TAP will continue to hold a valid TPA
                         work of pipelines running from Azerbaijan to  exemption beyond 2020, complying with the
                         Italy. The first two sections of the network, the  European regulation.” ™