                                                                                                  The Gazprom-owned
                                                                                                  Akademik Cherskiy is
                                                                                                  stationed at the German
                                                                                                  port of Mukran.





































       Denmark permits Gazprom to anchor




       vessels to finish Nord Stream 2




        DENMARK          DANISH regulators have granted the Gaz-  permission to build the pipeline in October last
                         prom-owned Nord Stream operating company  year. But the permit issued by the Danish Energy
                         permission to anchor pipelaying vessels, poten-  Agency (DEA) did not authorise Gazprom to
                         tially clearing a path for work on the pipeline to  anchor vessels. It requested a revision last month
                         resume.                              and that request has now been granted.
                           Construction of the 1,230-km Nord Stream   “The change means that the company can
                         2 is almost finished, with just a 120-km section  use pipelaying vessels with anchors, either
                         in Danish waters left to complete. But work was  independent or in combination with DP pipe-
                         halted in December when a Swiss contractor  laying vessels,” the DEA said in a statement on
                         suspended operations after the US slapped sanc-  July 6.
                         tions on the project. Russia has deployed its own   Nord Stream 2 is now anticipated to come on
                         pipelaying vessels to finish the job.  stream in early 2021, Russian officials have said,
                           Ship-tracking data shows that Russia has  more than a year behind schedule. It will flow up
                         two vessels, the Gazprom-owned Akademik  to 55bn cubic metres of gas to Germany, helping
                         Cherskiy and the Fortuna, belonging to Mos-  Gazprom reduce gas flows via Ukraine.
                         cow-based pipelaying company Mezhregion-  A bill is making its way through US Congress
                         truboprovodstroi (MRTS), currently stationed  that would impose additional sanctions on Nord
                         at the German port of Mukran.        Stream 2, but it is doubtful whether additional
                           It is understood that Cherskiy is equipped  measures would have an impact on the project
                         with the dynamic positioning (DP) system  at this stage. But the physical completion of the
                         required to work in Danish waters, but it lacks  pipeline is only one challenge that Gazprom is
                         a crane big enough for its 48-inch (1,220-mm)  facing. The EU has legislated to apply its third
                         pipes. Fortuna, on the other hand, does not have  energy package to the pipeline, meaning Gaz-
                         DP system but has a big enough crane.  prom may have to divest the pipeline and offered
                           After some delay, Denmark granted Gazprom  its flow capacity to third parties. ™