       Algeria’s 1-GW solar ambitions





       to bear first fruit by 2023






        ALBERIA          ALGERIA’S Solar 1,000 scheme is expected to  in December. The deadline for submitting pro-
                         begin generating electricity at the end of 2021,  posals was set for June 15, but was extended
                         when the 30-MW Beni Ounif solar park comes  following a request by local and international
                         online.                              investors that needed more time to conduct
                           The scheme, which aims to build 1 GW of  detailed financial and technical studies.
                         grid-connected solar capacity, is the first step   In the auction, the state will allocate the total
                         in Algeria’s plans to build 15 GW of renewable  capacity in lots of between 50 MW and 300 MW.
                         energy capacity by 2035.             As many as 11 sites have already been selected
                           Ismail Mougari, director-general of Shaems,  for the solar plants.
                         the state-owned company overseeing the large-  The Algerian government has already inau-
                         scale project, said that the solar park at Beni  gurated a 180-MW capacity solar panel factory
                         Ounif in Bechar Province could start producing  in Ouargla. Another 100-MW solar park will
                         power at the end of next year, or the beginning  also be built in the same province.
                         of 2024 at the latest.                 The country’s energy strategy aims to increase
                           The clean power generated by the Beni Ounif  the domestic renewable generation capacity to
                         solar farm will be sold exclusively to state-owned  22 GW, or 27% of the total domestic generation
                         electricity and natural gas distributor Sonelgaz  capacity, by 2030. Solar production will contrib-
                         for a period of 25 years, Mougari said.  ute more than 13.5 GW of the total.™
                           The call for tenders for the deployment of 1
                         GW of solar PV capacity across Algeria opened