       Earthquake disrupts Iranian oil activities





        IRAN             AN earthquake in southern Iran caused damage  is central to Tehran’s efforts to ease reliance on
                         to an important oil facility over the weekend,  Kharg island.
                         with state TV saying that production had been   The pipeline will carry crude from the oil-
                         disrupted.                           fields in the West Karoun cluster, linking the
                           The 5.9-magnitude tremor resulted in the  Gulf port city of Goreh to the Omidieh pumping
                         collapse of the control room roof at the Goreh  station, then on to the Bahregan and Jask termi-
                         pump station, with Gachsaran Oil & Gas Co.’s  nals for onward export.
                         (GOGC) managing director Houshang Seidali   Phase one of the 42-inch (1,067mm) 1,000-
                         quoted as saying that a turbine was forced out of  km pipeline will provide for the transportation
                         service. He added that some production was also  of 460,000 bpd and 254,000 bpd of heavy and
                         taken offline, but did not disclose the volume.  light Iranian crude, respectively. Crude will be
                           The Gachsaran oilfield has reserves of around  moved directly from the North Azadegan, South
                         1.1bn barrels with GOGC reportedly producing  Azadegan, Yadavaran, and Darkhovin oilfields,
                         in excess of 600,000 barrels per day (bpd) of oil  while supply from North Yaran will be moved to
                         and 1bn cubic feet (28mn cubic metres) per day  a facility at Jofair before onward transportation
                         of gas from the field as well as assets in Bushehr,  to the West Karoun station and beyond.
                         Fars, Khuzestan and Kogilouyeh-Boyrahmad.   Phase 2 is also underway, which will increase
                           The company also operates Goreh pump sta-  the capacity of the line to more than 1mn bpd.
                         tion and oil export facilities which feed the newly   The wider project will include five pumping
                         built 1mn-bpd Goreh-Jask pipeline allowing  stations, two pigging stations and terminals
                         Iran to export crude via a new terminal outside  and 20 500,000-barrel tanks with a capacity of
                         the Strait of Hormuz.                10mn barrels of oil as well as offshore facilities
                           Iran’s official Shana news agency said that the  for exporting crude oil.
                         only damage caused was to the roof of the con-  It forms part of a broader move by the Islamic
                         trol rooms in Goreh A and C pump houses, not-  Republic to increase its capabilities to export
                         ing that “no other significant damage has been  oil from facilities outside the Strait of Hormuz,
                         reported in other subsidiaries of the National  which has proven to be a flash point whenever
                         Oil Co.”                             tensions with neighbouring countries and/or
                           While the earthquake was felt at Iran’s key  the US flare up. The objective is to turn Jask into
                         Kharg island  oil  terminal,  through  which  “Iran’s key hub of oil exports,” according to Ira-
                         around 90% of the country’s exports currently  nian President Hassan Rouhani.
                         flow, Shana quoted Abbas Asadrouz, managing   In March, Petroleum Engineering and Devel-
                         director of Iranian Oil Terminals Co. as saying:  opment Co. (PEDEC) CEO Touraj Dehghani
                         “No damage has been inflicted on facilities of  said that the pipeline had reached 80% comple-
                         this company and activities are done normally.”  tion while the first single-point mooring (SPM)
                           The Goreh-Jask pipeline and terminal project  has been installed at Jask.™