Page 8 - MEOG Week 20 2021
P. 8

MEOG                                   PIPELINES & TRANSPORT                                           MEOG


       Iran completes




       Goreh-Jask pipeline




        IRAN             IRANIAN Oil Minister Bijan Zanganeh said this  Gulf port city of Goreh in Bushehr Province to
                         week that the first phase of the crude oil pipeline  the Omidieh pumping station, then on to the
                         linking oilfields of West Karoun with Jask on  Bahregan and Jask terminals for onward export.
                         the Sea of Oman has been completed ahead of   Phase one of the 42-inch (1,067-mm), 1,000-
                         exports beginning next month.        km pipeline will provide for the transportation
                           While the project is still to be inaugurated,  of 460,000 bpd and 254,000 bpd of heavy and
                         Zanganeh was quoted by official Iranian media  light Iranian crude respectively. Crude will be
                         as saying that “construction has finished” on the  moved directly from the North Azadegan, South
                         conduit, adding that the first cargo of crude will  Azadegan, Yadavaran and Darkhovin oilfields,
                         be exported from the new Jask Oil Terminal dur-  while supply from North Yaran will be moved to
                         ing the Iranian month of Khordad, which runs  a facility at Jofair before onward transportation
                         from May 22 until June 21.           to the West Karoun station and beyond.
                           Touraj Dehghani, managing director of the   Phase 2 is also underway, which will increase
                         Petroleum Engineering and Development Co.  the capacity of the line to more than 1mn bpd.
                         (PEDEC), the subsidiary of National Iranian   The wider project will include five pumping
                         Oil Co. (NIOC) that is overseeing the pipeline  stations, two pigging stations and terminals and
                         project, said earlier in May: “Close to 1,000 km  twenty 500,000-barrel tanks with a capacity of
                         of pipes are in place and the first phase of the pro-  10mn barrels of oil as well as offshore facilities
                         ject is scheduled to come on stream in May. It will  for exporting crude oil.
                         transfer 300,000 barrels of crude oil a day from   Iran has set out to reduce the vulnerability
                         Goreh oil terminal in Bushehr Province to Jask  of its oil exports to disruption. Around 90% of
                         Port in Hormozgan Province.”         exports are currently loaded at the Kharg Island
                           The pipeline will carry crude from the oil-  terminal and must pass through the Straits of
                         fields in the West Karoun cluster, linking the  Hormuz.™

















































       P8                                       www. NEWSBASE .com                           Week 20   19•May•2021
   3   4   5   6   7   8   9   10   11   12   13