Page 296 - Minutes of meeting
P. 296
1. Work Programme
th
Figure 1.1 Work Programme as of 10 April 2020
13/04 20/04 27/04 04/05 11/05 18/05 25/05 01/06 08/06 15/06 22/06 29/06 06/07 13/07 20/07 27/07
Week beginning
Draft Socio-Economic Narrative
Draft Appraisal Framework
Draft Project Long List
Receipt of Project Concepts
Finalisation of Communications Plan
Stakeholder and Social Media Engagement
Feedback and Due Dilligence of Project Concepts
Finalisation of Communications Plan
Appraisal of Concept Forms
Draft Options Appraisal Report
Town Investment Plan Skeleton Development
Town Deal Board Meeting
Focused Community Engagement
Draft Business Case Development for Short List Projects
Draft Economic Assessment Report for Town Investment Plan
Developing Draft Town Investment Plan
Preparation of Draft Communications Engagement Report
Town Deal Board Meeting
Finalisation of Business Cases for Short List Projects
Finalisation of Economic Assessment for Town Investment Plan
Finalisation of Communication and Engagement Report
Finalisation of Town Investment Plan
Town Deal Board Meeting
Town Investment Plan - Submission
Executive Summary document
Key
Work in progress
Town Deal Board
Output
Plan Development
Scheme Development
Communications and Engagement