Buildings and Grounds

               Projects

               -      The Building Automation project at Rich South is still underway.  We were originally
               waiting until spring break to shut down systems for upgrade, but due to the current emergency
               closing we are able to accomplish that earlier.  We have given strict guidelines to the contractor
               which include a crew of only 1-3 people, a list of areas each day they will be working so we can
               clean and disinfect behind them, proper social distancing with persons in the building, and that no
               worker be on site that has any symptoms of illness.  This project is running on time and we don’t
               anticipate any delays associated with the Covid-19 situation.

               -      The asbestos abatement projects that were outlines last month are still moving forward over
               the week of Spring Break.  The District has posted the information to each schools web page along
               with the Buildings and Grounds web page.


               Updates
               -      The Buildings and Grounds Department is still working during the shutdown, but we have
               altered work times and shifts in order to keep our staff in a safe working environment while also
               continuing to clean and disinfect areas of the buildings that have had people in them throughout the
               day.  We are running two custodial shifts, one in the AM and one in the PM, with reduced amounts
               of staff per day working on a rotational basis.  Our grounds and maintenance crews are also
               working on a shorter rotational basis in order to maintain our vital systems and perform necessary
               maintenance work.

               -      Our campuses have begun their spring applications of fertilizer and weed control.  We
               follow the required posting guidelines for herbicide and pesticide applications.  Our grounds staff
               that applies the product is trained and certified through the State of Illinois to perform the work
               safely and properly. They are required to maintain the proper certifications and are retested and re-
               certified every three years.




               Business Office

               Financial Information

               Attached is the fund balance summary report. This information shows the fund balance by fund
               through March 31, 2020. The balances include the proceeds from the series 2020A bonds and the
               2019 March property tax payments. Once the bond proceeds are removed from the fund balances,
               the eight-month financial activities yields a surplus of $10.2 million.