ANNEXURE 3:  FORMAT OF AN INFRASTRUCTURE PLAN





                       2.  Demand or need determination

                          The reasons for the proposed new infrastructure should be provided, based on changes in
                          the population demand or need for services.

                       Information such as growth in the population, in-migration, ratios of staff to beneficiaries, and
                       increases in transaction volumes could all be used to show changes in service demand.

                       3.  Accessibility study

                          Accessibility studies are used to quantify the extent of service demand and the supply of
                          government  service points required to meet this demand.  This section should cover the
                          following:

                          ■  The results of accessibility studies undertaken.

                          ■  Information on the geographic accessibility of existing services points.

                          ■  Areas of poor accessibility could be highlighted through the use of accessibility maps.
                          ■  The optimal number and location of new service points.

                          ■  Service points that should be given priority in rolling out the infrastructure plan.

                          ■  Service points that should be considered for closure or relocation.

                       4.  Asset management

                          This section should present the plans, standards, and specifications and costs for managing
                          existing  and new infrastructure.   It should also describe the standards to be used in the
                          infrastructure  design, service provisioning and staffing.

                       5.  Financial summary

                          The financial  summary provides  information on  historical and  future expenditure  on the
                          maintenance  and construction of infrastructure.  It also indicates from where the funds will
                          be sourced.
                       6.  Monitoring and evaluation


                          This section describes how the implementation of the infrastructure plan will be monitored
                          and evaluated.  A logic model can be used to define the output and outcome indicators that
                          will be used  to do the monitoring and evaluation.   Such monitoring and evaluation could
                          assist in identifying possible needs to adjust the infrastructure plan.

                       7.  Supporting documentation

                          A financial budget and an executive summary should be added to the document.  Furthermore,
                          any references or supporting documents should be included in a References and Appendices
                          section in the Plan.