LOCATION: Temple, TX                                                                        PROJECT PROFILES
                                                                                                                                                   CLIENT: Confidential
                                                                                                                                                   GENERAL CONTRACTOR: JE Dunn
                                                                                                                                                   BUDGET: $800 Million

                                                                                                                                                   The new Temple Data Center is an $800 million data center building and site
          TEMPLE                                                                                                                                   infrastructure in an industrial park located 50 miles north of the Austin Metro
                                                                                                                                                   area. Starting in July 2022, Rosendin expects to hire 440 craft workers and staff
                                                                                                                                                   in Temple. This includes skilled electrical workers with the IBEW Local 72, as well
                                                                                                                                                   as prefabrication warehouse staff, BIM experts, estimators, project managers,
                                                                                                                                                   and office staff. The 900,000 SF data center aims to serve as a model of energy
                                                                                                                                                   efficiency and will be supported by renewable energy from new solar energy
          DATA CENTER                                                                                                                              plants. The project will also aim for LEED Gold certification and receive credits
                                                                                                                                                   for water restoration efforts. This build will create a total of 1,200 jobs during
                                                                                                                                                   construction at the 400-acre site.