Page 14 - INSTRUMENTED PILE LOAD TEST ON SOFT GROUND
P. 14

Maintained Load Test (MLT) –



  Preliminary and Working Pile Load Test





       Maintained Load Test (MLT): A loading test in which each increment or                         By using Limit State Design (e.g., Eurocode 7-EC7), the preliminary pile test
       decrement of load is held constant either for a defined period of time or                     and working pile test allow to adopt less conservative partial factors when
       until the rate of settlement or rebound falls to a specified value.                           reducing unfactored shaft friction and end-bearing, resulting in a more

                                                                                                     economical design


       Preliminary pile load test (Failure Load Test): Typically carried out before                  Kentledge (dead weight used in loading test) reaction system (stacking up
       piling works commence. To adequately verify shaft friction and end-                           concrete block or steel plated as counterweight is customarily use due to
       bearing capacity, the piles are loaded 3 times the working load (more than                    the easy interpretation of the test results.
       300%) or until failure (Failure load test – sacrificial pile)


       Working pile load test: Typically carried out during piling or when                           Too high loads (ground support bearing capacity?): Some codes (e.g.,
       substantial piling works are completed. The piles are loaded 2 times the                      Eurocode 7-EC7) allow results of pile load test to be extrapolated for a pile
       working load ( less than 200%)                                                                diameter not exceeding 2 times







                                                                                                                                                         Note
                                           Preliminary pile test         1 pile or 0.5% of the total number of working piles, whichever is greater
                                                                                                                                                         Working Load:
                                                                                                                                                         The load which the pile is designed
                                           Working pile test             2 piles or 1% of the total number of working piles or 1 for every 50 meters     to carry without exceeding the
                                                                         length of proposed building, whichever is greater
                                                                                                                                                         allowable settlement
   9   10   11   12   13   14   15   16   17   18   19