Page 15 - INSTRUMENTED PILE LOAD TEST ON SOFT GROUND
P. 15

Test Procedure – Failure Load Test






   Loading % of         Time of Holding (minutes)                                                                                                             Note:
   Working Load
                                                                                                                                                              Driven pile selected for testing
   0                    10                                                                                                                                    shall not be loaded after
   10                   10                                                                                                                                    installation
   20                   10
   30                   10
   40                   10                                                                                                                                    The minimum required time
   50                   10                                                                                                                                    lapse is at least 14 days
   60                   10
   70                   10
   80                   10
   90                   10
   100                  60 min or settlement rate less than 0.25 mm/hr (whichever is longer)
   75                   10
   50                   10
   25                   10
   0                    30                                                                     10. Interpretation of Test Results
   25                   10                                                                     10.1 The S.O.'s interpretation and conclusions on the test results shall be
   50                   10
   ...200               60 min or settlement rate less than 0.25 mm/hr (whichever is longer)   final. The pile so tested shall be deemed to have failed if:
   150                  10
   100                  10                                                                     a) The residual settlement after removal of the test load exceeds 6.5mm;
   50                   10
   0                    30
   50                   10                                                                     OR
   100                  10
   …300                 60 min or settlement rate less than 0.25 mm/hr (whichever is longer)   b) The total settlement under the Design Load exceeds 12.5mm;
   200                  10
   100                  10
   0                    30                                                                     OR


                                                                                               c) The total settlement under twice the Design Load exceeds 38.0mm, or
                                                                                                  10% of pile diameter/width, whichever is the lower value.
   10   11   12   13   14   15   16   17   18   19   20