Page 12 - BULETIN GEOTEKNIK 2023
P. 12
Installation sequence of
geopolymatress at project
METHOD
METHOD
of “Pembinaan Jalan Baru
INSTALLATION
INSTALLATION
dari Bagan Sungai Pinang
ke Kampung Pulau
Betong, Balik Pulau,
Pulau Pinang” are divided
into 3 phases due to
working space constraint
and existing road is used
by the villagers.
01
The unsuitable material is to be
excavated to the groundwater level,
commonly found at the depth between
1 to 1.5m below ground level.
02
Geopolymatress is placed on top of the
geotextile separator and glued by using
polyurethane foam to form a solid
homogeneous mattress-like layer.
03
Once the formation level was
encountered, A layer of high strength
geotextile separator is placed to separate
between the soil and geopolymatress.
04
50mm thick lean concrete is constructed for
levelling purpose and 300mm thick concrete
slab with 2 layer of BRC A12 is constructed as a
counterweight for the geopolymatress.
10