DESCRIPTIONS OF CURRENT SECTION 16:2014
Ref. Standard Specification Content
Specification for
Road Works :
Section 16
16.4 Guniting 16.4.10 (f) The Contractor shall engage a specialist geotechnical engineer accredited by BEM
or ACEM/IEM, to study and propose rectification works, when defective works are identified
and directed by the S.O. The Contractor shall be fully responsible for the costs, time delay in
works and other incidental consequences for the defective works. The proposed
rectification works, if accepted by the S.O., shall be carried out at the Contractor's own
costs.