Page 7 - How do I set up a FIXED Contract
P. 7
Setting up a FIXED Contract
1
2
3 4
1. Review the Price Type. This field should be Amount.
2. Review the Product. This value should be FIXED_CT.
Price Type and Product are not editable on this screen. However, if you need to change these values, you will need to refer
to the Job Aid that will guide through the steps to change product.
3. Review the Project(s).
4. Review the Activities.
The Activity may be YRALL for these types of contracts where no detailed billing schedule.
5. Close the browser window and navigate back to the Contract Setup page. Click the Refresh button
to repopulate the Contract Setup page with new contract data.
F. Review Contract Lines – Billing Plan Status