Page 252 - GM Booklet Dec 2022 demo2
P. 252

As per Railway Board Gati Shakti unit has been allotted 12 Nos. of Supervisors, 12 Nos. of
               Technicians and 24 Nos. Group D Staff.(Ref RB lr. No. E(NG)I/2022/TR/32 dt. 13.09.2022)

                                                        Staff Position
               S.No         Category         Recommended by RB            Present Strength         Short Fall

                 1        Supervisors                   12                         4                    8
                 2        Technicians                   12                         -                   12
                 3          Group D                     24                         -                   24
                 4           Steno                       -                         1                    -

               Works allotted and Progress

                                          Plan Head                           No of works allotted
                        PH 1600 (Traffic Facility)                                      3
                        PH 3000 (ROB/RUB)                                               12
                        PH 4200 (Workshop)                                              1
                        PH 5300 (Passenger Amenities)                                   2
                        Bye Pass Works (FLS)                                            1

               Status / Progress of works

            PH 1600 (Traffic Facility)
            S.N               Name of work                 Year of  Estimat                Present Status
                                                           Sanctio    ed Cost
                                                               n
              1    Nizamabad-Remodelling  of  yard  2018-19  Rs.8.79              Tender  will  be  floated  within  a
                   arrangements        for     providing                84 cr     week  after  sanctioning  of  Phase
                   additional  platforms  and  one  full                          II work by RB.
                   length dead end spur.                                          TDC - 10.02.2023.
              2    Janakampet  Jn-Provision  of  two  2021-22  Rs.11.3            Agency finalised (Sept 22). Work
                   Additional  loop  lines  to  cater  the              062cr     is Progress.
                   operational needs.
              3    Falaknuma - Provision of DN loop         2021–        Rs.      Agency finalised (Sept 22). Work
                   line (Standard Double line layout). 22              8.5721     is Progress.
                                                                          cr
            PH 5300 (Passenger Amenities)
              1    Kamareddi-Provision of 02 no.s of        2021–     Rs. 0.72  P.O. released for 2nd lift, call for
                   Lifts at Kamareddi station.                22          cr      RITES inspection to be given by
                                                                                  agency. TDC - Dec 2022.
            Work related to CMLR Workshop/Kurnool
              1    SC  –  DHNE  section:  Alampur  -                  -           Planning  for  execution  of  works
                   Road:      Execution      of     Yard                          shall be done along with Sr DOM
                   remodelling      works      including                          to  avoid  the  hindrance  to  traffic
                   formation  treatment  at  Alampur                              movement  to  the  maximum
                   Road  station  in  connection  setting                         extent.
                   up  Coach  Mid  Life  Rehabilitation                           TDC - July 2023.
                   Work Shop at Kurnool City.