Page 252 - GM Booklet Dec 2022 demo2
P. 252
As per Railway Board Gati Shakti unit has been allotted 12 Nos. of Supervisors, 12 Nos. of
Technicians and 24 Nos. Group D Staff.(Ref RB lr. No. E(NG)I/2022/TR/32 dt. 13.09.2022)
Staff Position
S.No Category Recommended by RB Present Strength Short Fall
1 Supervisors 12 4 8
2 Technicians 12 - 12
3 Group D 24 - 24
4 Steno - 1 -
Works allotted and Progress
Plan Head No of works allotted
PH 1600 (Traffic Facility) 3
PH 3000 (ROB/RUB) 12
PH 4200 (Workshop) 1
PH 5300 (Passenger Amenities) 2
Bye Pass Works (FLS) 1
Status / Progress of works
PH 1600 (Traffic Facility)
S.N Name of work Year of Estimat Present Status
Sanctio ed Cost
n
1 Nizamabad-Remodelling of yard 2018-19 Rs.8.79 Tender will be floated within a
arrangements for providing 84 cr week after sanctioning of Phase
additional platforms and one full II work by RB.
length dead end spur. TDC - 10.02.2023.
2 Janakampet Jn-Provision of two 2021-22 Rs.11.3 Agency finalised (Sept 22). Work
Additional loop lines to cater the 062cr is Progress.
operational needs.
3 Falaknuma - Provision of DN loop 2021– Rs. Agency finalised (Sept 22). Work
line (Standard Double line layout). 22 8.5721 is Progress.
cr
PH 5300 (Passenger Amenities)
1 Kamareddi-Provision of 02 no.s of 2021– Rs. 0.72 P.O. released for 2nd lift, call for
Lifts at Kamareddi station. 22 cr RITES inspection to be given by
agency. TDC - Dec 2022.
Work related to CMLR Workshop/Kurnool
1 SC – DHNE section: Alampur - - Planning for execution of works
Road: Execution of Yard shall be done along with Sr DOM
remodelling works including to avoid the hindrance to traffic
formation treatment at Alampur movement to the maximum
Road station in connection setting extent.
up Coach Mid Life Rehabilitation TDC - July 2023.
Work Shop at Kurnool City.
250