8    238d          Sec-bad-Mudkhed- ROB in lieu         2019-20  Alignment  submitted  by  State
                                 of LC 228  Wadiyaram Yard-                       Government (July 2022).
                                 Masaipet at  Km 555/3-4.                         GAD  prepared  and  submitted  to
                                                                                  Div    (23.11.2022)     for   initial
                                                                                  comments.
              9    238f          Sec-bad-Mudkhed- ROB @ LC            2019-20  Joint  inspection  conducted    with
                                 No.250 (Bolarum Yard) - Cavalry                  HRDCL          authorities       on
                                 barrack.                                         29.11.2022      for    fixing    up
                                                                                  alignment plan for preparation of
                                                                                  GAD.
             10  238g            Sec-bad-Mudkhed-ROB @ LC             2019-20  Soil  particulars  and  trial  pit
                                 No.209 A uppalvai-                               details  to  be  incorporated  in
                                 Kamaredddi                                       GAD.  Boring  to  collect  Soil
                                                                                  particulars             completed
                                                                                  (22.11.2022)  and  details  are
                                                                                  being  incorporated  in  GAD,
                                                                                  under progress.
             11  238h            Jankampet-Bodhan- ROB @ LC  2019-20  GAD                  under      revision,    as
                                 No. 12JB at km 12/5-6                            submitted by construction having
                                                                                  some  infringement  issue  for
                                                                                  future doubling/tripling.
             12  238j            Jankampet-Bodhan- ROB @ LC  2019-20  GAD uploaded on e-DAS for
                                 No. 18JB at km 19/1-2                            Division Approval on 09.11.2022.
                                 (Bodhan Yard)                                    After approval of GAD by Rly, will
                                                                                  be sent to state govt for approval
                                                                                  and estimation.

            PH 4200 (Workshop work)
            S.N    Name of work                    Year      of  Estimated      Present Status
            o                                      Sanction      Cost
              1    Integrated  Bogie  Assembly  2019-20          Rs.  15.15  98%  civil  works  completed.  Indent
                   and  Disassembly  for  LGD                    cr             for machinery  has  been  placed  by
                   shops.                                                       Mech/HQ to COFMOW Rs. 14cr.
                                                                                Tender  opened  by  COFMOW  on
                                                                                30.06.2022. The case file has been
                                                                                transferred  to  NR  for  finalisation,
                                                                                due to closure of COFMOW.

             PH 1600 (Traffic Facility – Bye pass lines)
             S.No.  Name of work                          Present Status
               1     Nizamabad Bye pass line              Quotation  for  FLS  was  issued  on  12.08.2022.  FLS
                     (FLS Survey)                         Survey is under progress.
                                                          One alignment of about 1 km length of 4 degree curve
                                                          is  finalized  by  Construction.  Work  has  been  handed
                                                          over by Con and ROR calculation in process.
                                                          There are corrections (Land Value & ESP of NZM) and
                                                          are being attended.