8 238d Sec-bad-Mudkhed- ROB in lieu 2019-20 Alignment submitted by State
of LC 228 Wadiyaram Yard- Government (July 2022).
Masaipet at Km 555/3-4. GAD prepared and submitted to
Div (23.11.2022) for initial
comments.
9 238f Sec-bad-Mudkhed- ROB @ LC 2019-20 Joint inspection conducted with
No.250 (Bolarum Yard) - Cavalry HRDCL authorities on
barrack. 29.11.2022 for fixing up
alignment plan for preparation of
GAD.
10 238g Sec-bad-Mudkhed-ROB @ LC 2019-20 Soil particulars and trial pit
No.209 A uppalvai- details to be incorporated in
Kamaredddi GAD. Boring to collect Soil
particulars completed
(22.11.2022) and details are
being incorporated in GAD,
under progress.
11 238h Jankampet-Bodhan- ROB @ LC 2019-20 GAD under revision, as
No. 12JB at km 12/5-6 submitted by construction having
some infringement issue for
future doubling/tripling.
12 238j Jankampet-Bodhan- ROB @ LC 2019-20 GAD uploaded on e-DAS for
No. 18JB at km 19/1-2 Division Approval on 09.11.2022.
(Bodhan Yard) After approval of GAD by Rly, will
be sent to state govt for approval
and estimation.
PH 4200 (Workshop work)
S.N Name of work Year of Estimated Present Status
o Sanction Cost
1 Integrated Bogie Assembly 2019-20 Rs. 15.15 98% civil works completed. Indent
and Disassembly for LGD cr for machinery has been placed by
shops. Mech/HQ to COFMOW Rs. 14cr.
Tender opened by COFMOW on
30.06.2022. The case file has been
transferred to NR for finalisation,
due to closure of COFMOW.
PH 1600 (Traffic Facility – Bye pass lines)
S.No. Name of work Present Status
1 Nizamabad Bye pass line Quotation for FLS was issued on 12.08.2022. FLS
(FLS Survey) Survey is under progress.
One alignment of about 1 km length of 4 degree curve
is finalized by Construction. Work has been handed
over by Con and ROR calculation in process.
There are corrections (Land Value & ESP of NZM) and
are being attended.