Work related to Redevelopment of Kacheguda Railway Station
1 Redevelopment of Kacheguda 2021-22 - The meeting regarding KCG
Railway Station of Hyderabad station development to be held
Division, SCR. on 30.11.2022.
PH 3000 (ROB/RUB works)
S.N PB No. Name of work Year of Present Status
o. Sanc
1 121 RUB near Safilguda lane in lieu 2001-02 A letter dt 08/11/2022 given to
of LC No 254 GHMC regarding closure of LC
due undertaking of capacity
enhancement works (PF
extension etc).
2 145 ROB between Dichpally - 2012-13 Foundation design submitted to
Nizamabad two lane in lieu of HQrs on 18.11.2022, under proof
LC No 193 check.Joint inspection/relocation
of S&T and Telecom cable
conducted on 23.11.2022.
To take up the foundation work
S&T cable to be shifted.
TDC - Oct 2023.
3 220 ROB between Gundla 2017-18 Combined estimate preparation
Pochampally - Medchal four is pending due to non-receipt of
lane in lieu of LC No 246/A approach estimate from State
Govt. State Govt. has been again
requested on 28.11.2022 to
submit their portion of estimate.
4 192 ROB between Mahboobnagar - 2016-17 State Govt is finalising the
Manyamkonda in lieu of LC No alignment plan and will submit to
60 Rly shortly, as per their letter
dated 17.11.2022.
5 234 ROB between Falaknuma - 2018-19 Tender opened on 28.10.2022
Budvel four lane in lieu of LC and under finalisation.
No 7 Permission to HMWSSB for
shifting their water supply line in
Railway area is under process.
6 232 ROB between Timmapur - 2018-19 State Government given initial
Shadnagar four lane in lieu of approval of GAD on 22.11.2022
LC No 27 and submitted to Division for
review. Estimate under
preparation.
7 238c Proposed ROB as 1x46.00M 2019-20 Alignment plan received from
clear span composite steel State Govt in July 2022. GAD
girder at Km 166/500-600 in lieu under preparation.
of Existing Manned LCNo.90A
between Wanaparthy road and
Sriramnagar stations.