Page 38 - CompleteBooklet2021
P. 38
3. Elimination of Manned Level Crossings
Hyderabad Division has achieved the highest progress in Elimination of Manned
Level Crossing gates in the Zone for the year 2020-21.
2020-21 2021-22
Sl
No Description of item Boards Internal Progress Boards Internal Progress
Target Target Target Target (22.10.21)
Construction of Road Over
1 - - - - - -
Bridge
Construction of Limited
2 10 12 14 09 21 03
Height Subways
Closure of Level crossings on
3 - - - - - -
account of diversion of Traffic
Closure of Level crossings on
4 - - - - - -
account of meager traffic
On 25.5.2021, as a part of RUB work in lieu of Manned Level Crossing No: 62/E ,
RCC boxes have been launched duly taking a single traffic block of 08 Hrs. The
work has been taken up without RH girder insertion, as the said location is on 4
degree curve.
On 13.06.2021, Division has eliminated LC No: 25/E between TMX-SHNR stations
by providing RUB duly taking a single block of 10 Hrs without RH girder insertion as
the location was on 3 Degree curve.
35