Page 40 - CompleteBooklet2021
P. 40

  The work of Canal Crossing between BLSA –KEK stations of SC-MUE section at
                   Km  404/300-400  was  taken  up  and  completed.  Girder  insertion  was  done  on
                   01.06.2021 and was further  removed after provision of RCC box on 13.06.2021.














            7. Increase in Sectional Speeds and New lines.

               a.  Sectional Speeds

                 FM-DHNE Section – CRS sanction received for Raising of sectional speed from 100
                   to 110 Kmph on 02.12.2020 and same has been implemented.

                 SHNR  –GLY  (New  Double  Line)  –  Double  line  commissioned  in  the  month  of
                   Sept‟20  with  MPS  75  Kmph  and  increasing  of  speed  from  75  to  100  Kmph
                   implemented in March‟21.

                 GWD  –  PASR  (27.36  Km)  between  Gadwal  –  Raichur  Section  –  The  sectional
                   speed has been increased from 60 Kmph to 100 Kmph on 14.08.2021.


               b.  New Lines

                 Jaklair – Makthal - new line (11 Km) – Commissioned in the month of June‟20, to be
                   taken over by open line from construction.

                 Manoharabad  –  Gajwel  -  new  line  (33  Km)  –  Commissioned  in  the  month  of
                   June‟20, to be taken over by open line from construction.

                 Shadnagar  –  Gollapalli  –  Double  line  (DN  Line) (30 Km) – Commissioned in the
                   month  of Sept‟20, taken over by open line.

                 Falaknuma - Umdanagar– Double line (DN Line) (14 Km) – Commissioned in the
                   month  of March‟21, taken over by open line.

                 Umdanagar – Shadnagar - Double line (DN Line) (29.76 Km) – Commissioned in
                   the month  of July  ‟21, taken over by open line.


            8. Special Achievements made in Track and Bridge works.

                 On  13.6.2021  Division has achieved a progress of 3.650 Km of Deep Screening
                   on  a  single  day  (with  2  machines  ie  1.800  Km  +1.850  Km)  between  SHNR-BABR
                   stations on UP line in the shadow of RVNL Bridge block. This is probably highest ever
                   single day progress of BCM.

                                                            37
   35   36   37   38   39   40   41   42   43   44   45