The work of Canal Crossing between BLSA –KEK stations of SC-MUE section at
Km 404/300-400 was taken up and completed. Girder insertion was done on
01.06.2021 and was further removed after provision of RCC box on 13.06.2021.
7. Increase in Sectional Speeds and New lines.
a. Sectional Speeds
FM-DHNE Section – CRS sanction received for Raising of sectional speed from 100
to 110 Kmph on 02.12.2020 and same has been implemented.
SHNR –GLY (New Double Line) – Double line commissioned in the month of
Sept‟20 with MPS 75 Kmph and increasing of speed from 75 to 100 Kmph
implemented in March‟21.
GWD – PASR (27.36 Km) between Gadwal – Raichur Section – The sectional
speed has been increased from 60 Kmph to 100 Kmph on 14.08.2021.
b. New Lines
Jaklair – Makthal - new line (11 Km) – Commissioned in the month of June‟20, to be
taken over by open line from construction.
Manoharabad – Gajwel - new line (33 Km) – Commissioned in the month of
June‟20, to be taken over by open line from construction.
Shadnagar – Gollapalli – Double line (DN Line) (30 Km) – Commissioned in the
month of Sept‟20, taken over by open line.
Falaknuma - Umdanagar– Double line (DN Line) (14 Km) – Commissioned in the
month of March‟21, taken over by open line.
Umdanagar – Shadnagar - Double line (DN Line) (29.76 Km) – Commissioned in
the month of July ‟21, taken over by open line.
8. Special Achievements made in Track and Bridge works.
On 13.6.2021 Division has achieved a progress of 3.650 Km of Deep Screening
on a single day (with 2 machines ie 1.800 Km +1.850 Km) between SHNR-BABR
stations on UP line in the shadow of RVNL Bridge block. This is probably highest ever
single day progress of BCM.