Page 39 - CompleteBooklet2021
P. 39
4. Progress of Deep Screening with BCM machine
2020-21 2021-22
Item
Target Progress Target Progress up to 22.10.21
Deep Screening with BCM 70 Km 81 Km 80 Km 65.300 Km
On 13.6.2021 HYB division has achieved highest ever BCM progress of 3.65 Kms
with 2 machines (1.800 Km +1.850 Km) between SHNR-BABR stations on UP line in
the shadow of RVNL Bridge block. This is probably highest ever single day progress
of BCM.
Deep screening work with BCM in the section.
5. Relaxation of Permanent Speed Restrictions.
Target 2021-22 = 02 Nos
Completed = 03 Nos
Sl
No Section Bet Stns Km /TP SR Reason for SR Remarks
Entering into single
1 SC-DHNE FM Yd 15/0-100 30 Kmph Deleted
linen from Double line
Pt No: 13B laid in Deleted on DN
2 SC-DHNE BDVL Yd 20/900-21/0 60 Kmph
transition line and relaxed
Pt No: 7B laid in to 100 Kmph on
3 SC-DHNE UR Yd 27/300-200 60 Kmph
transition UP line.
6. Canal Crossing Works:
Canal Crossing work between KEK-DAB stations in SC-MUE section is completed
duly inserting the girder on 16.05.2020 and further the girder has been removed after
completing the box casting work under the track on 29.07.2020.
36