Project Schedule
JC White is committed to being a partner and trusted advisor to our clients. To ensure a
smooth order and delivery process, we are requesting a project meeting before order
placement to verify all specifications, finishes and quantities. This process is critical to a
successful installation and may extend the overall lead time but we feel it is critical for a
successful end result. After bid award, JC White will do everything we can to work within
TTI’s projected move dates, however, we will also like to set achievable expectations.
PHASE 1 PHASE 2 PHASE 3
Specification Procurement Installation
Receipt of PO to JC White Verification of Site Conditions
Bid Award Notification
Meeting to Confirm All Receipt of deposit to JC
Products and Specifications White Workstation Furniture Delivery
Office Furniture Delivery
Order double check
performed
Board Room and Conference
Order entered and PO’s sent Furniture Delivery
to manufacturers
Ship dates confirmed and Ancillary Furniture Delivery
items scheduled for
installation
All Chairs