                   EDITION 08/25                                                  BÖLLINGHAUS HIGHLIGHTS







      UPDATE DYNAMICS






     The measures discussed and decided on in June have


     now been planned and dates fixed. From week 35 on,


     GOB will be on-site every two weeks, with at least two

     consultants, supporting the Böllinghaus colleagues to


     test what is already available and to further develop the


     new system. These activities will replace the current sprint planning which

     ends by end of August. To further improve the usage of the system and


     give people the chance to get more accustomed with it, we will try to


     develop some kind of “homework”-program for the weeks in between.

     In parallel we started setting up a new test environment which is about to


     be completed, with realistic data in it, to be able to simulate real processes.
















      TÜV RHEINLAND AUDIT







    The PED, CE Mark and UKCA external audit was

    carried out by TÜV Rheinland on 06.-07.08.25.


    The aim of the audit was to assess the conformity


    of the processes in accordance with the regulatory requirements applicable


    to PED products (Pressure Equipment Directive) and CPR/CE Mark for

    products used in the construction sector in general, and in particular for the


    United Kingdom (UKCA).

    As a result of this audit, no non-conformities were identified but the


    auditor suggested 4 opportunities for improvement which will contribute


    to the continuous improvement of Böllinghaus Steel' Integrated

    Management System (IMS).


    We thank you for your support!