Page 35 - Gi_April2021
P. 35

FIGURE 8 COMPLETED METALIIC TESTS AND CROSS SECTIONS  FIGURE 9 THE TRIALS CARRIED OUT INSIDE THE EXCAVATION















                 PE pipe and metallic mains which was
                 safer, quicker and at a lower cost when
                 compared to existing techniques. On
                 completion of the in-house tests and
                 field trials, the project was determined
                 a success due to the following:  FIGURE 10 FIELD TRIALS USING LONG-HANDLED TOOLNG OUTSIDE THE EXCAVATION
                    Small excavations can be achieved by
                  utilising long-handled tooling.
                    Increased safety by moving the
                  operative away from foam mixing
                  elements
                    Reduced cost compared to existing
                  techniques
                    Reduction in time for the operative to
                  apply the product
                   Following the completion of this
                 project, there were a number of lessons
                 learned. For example, it is important to
                 outline the problem early in the project
                 to provide focus and direction for the
                 project. Also, it’s important to ensure
                 that the product is integrated into the
                 business and there is early engagement
                 with key areas within the business. I
                 was able to achieve this by witnessing
                 operations and by creating a working
                 group within SGN with regular updates
                 on the progress of the project.
                   I effectively managed the project
                 throughout the development stages until
                 the final product was implemented.
                 I liaised with partners and other
                 departments, developing good working
                 relations and gaining real-time feedback
                 on the product’s progression. I delivered
                 a project that met the objectives stated
                 and followed the correct procedure for
                 producing an innovation product.
                   The Burstpack product has since
                 been deployed within SGN and is now
                 available to other GDNs and pipeline
                 businesses.

                  Acknowledgements                FIGURE 11 SUCCESSFUL SEAL OF ANNULAR SPACE
                  I owe a great thanks to several people who have
                  provided invaluable guidance and support throughout
                  the duration of this project. My deepest thanks go
                  to the members of staff within the research and
                  development team at Steve Vick International and
                  the SGN departments who supported this project,
                  in particular the managers and staff within the
                  operations, policy and health and safety teams. I also
                  wish to thank my innovation department managers
                  for their guidance and support throughout this
                  project. Support from all those involved have provided
                  valuable information, expanding my knowledge and            COMPLETE SEAL
                  understanding in key subject areas.


                                                                                                                        35



                                                                                                                  11/03/2021   08:19
        IGEMNews_YPPC.indd   4
        IGEMNews_YPPC.indd   4                                                                                    11/03/2021   08:19
   30   31   32   33   34   35   36   37   38   39   40