Page 35 - Gi_April2021
P. 35
FIGURE 8 COMPLETED METALIIC TESTS AND CROSS SECTIONS FIGURE 9 THE TRIALS CARRIED OUT INSIDE THE EXCAVATION
PE pipe and metallic mains which was
safer, quicker and at a lower cost when
compared to existing techniques. On
completion of the in-house tests and
field trials, the project was determined
a success due to the following: FIGURE 10 FIELD TRIALS USING LONG-HANDLED TOOLNG OUTSIDE THE EXCAVATION
Small excavations can be achieved by
utilising long-handled tooling.
Increased safety by moving the
operative away from foam mixing
elements
Reduced cost compared to existing
techniques
Reduction in time for the operative to
apply the product
Following the completion of this
project, there were a number of lessons
learned. For example, it is important to
outline the problem early in the project
to provide focus and direction for the
project. Also, it’s important to ensure
that the product is integrated into the
business and there is early engagement
with key areas within the business. I
was able to achieve this by witnessing
operations and by creating a working
group within SGN with regular updates
on the progress of the project.
I effectively managed the project
throughout the development stages until
the final product was implemented.
I liaised with partners and other
departments, developing good working
relations and gaining real-time feedback
on the product’s progression. I delivered
a project that met the objectives stated
and followed the correct procedure for
producing an innovation product.
The Burstpack product has since
been deployed within SGN and is now
available to other GDNs and pipeline
businesses.
Acknowledgements FIGURE 11 SUCCESSFUL SEAL OF ANNULAR SPACE
I owe a great thanks to several people who have
provided invaluable guidance and support throughout
the duration of this project. My deepest thanks go
to the members of staff within the research and
development team at Steve Vick International and
the SGN departments who supported this project,
in particular the managers and staff within the
operations, policy and health and safety teams. I also
wish to thank my innovation department managers
for their guidance and support throughout this
project. Support from all those involved have provided
valuable information, expanding my knowledge and COMPLETE SEAL
understanding in key subject areas.
35
11/03/2021 08:19
IGEMNews_YPPC.indd 4
IGEMNews_YPPC.indd 4 11/03/2021 08:19