Page 4 - Priesgaisrine signalizacija FX 3NET_Schneider Electric_Projktavimo instrukcija_ENG
P. 4
Planning Instruction 66571758GB0 Fire Detection 4
1.3 Regulations
EN54-14 “Guidelines for Planning, Installation, Commissioning and Maintenance” defines good general guidelines
for planning. Local specific regulations must also be followed.
The main planning and documentation phases are described in the diagram below. A typical lay out drawing
including devices is found in the section 1.4.
End user
Third party periodical inspection
Maintenance Maintenance
Use
Third party approval and/or handover
Installation Commissioning Commissioning and verification
Initialisation and configuration
Alteration,
modification or
Installation extension
Planning and design
Planning Assessment of needs or
Risk Assessment
Initial concept
© 2009 Schneider Electric. All rights reserved.
Standard EN54-14: Guidelines for planning
Schneider Electric Pelco Finland Oy Kalkkipellontie 6, 02650 Espoo, Finland Telephone: +358 10 446 511 Fax: +358 10 446 5103 www.pelco.com/nordic
Document Number 66571758GB0 49 2011