Page 6 - Tunneling
P. 6

TUNNELING                                                                  The excellence of collaboration


            Project for the Diversion of the Acheloos River –

            Acheloos River Diversion Tunnel to Thessalia





            1. SHORT HISTORY:                                    frames, etc.
            The partial diversion of the Acheloos River to Thessalia is a  In more detail, the following works took place: Establishment
            complicate and complex Technical project, whose construction  of trigonometrical network (horizontal and leveling) inside and
            design studies started thirty years ago.             outside the tunnel with high accuracy for the correct guidance
                                                                 of its excavation.
            In 1995, after annulling decisions, a new Total Environmental
            Impact Study was drawn up, and the initial design was amended  - Horizontal Network :
            as follows:                                          The horizontal network depended on fixed points, which existed
              A) The quantity of the diverted water was decreased to 600  before the original opening of the fronts, establishing at least
              million cubic meters annually                      two new ones at their entrances.
              B) The currently applicable Diversion Scheme was formulated,   •   Internally
              and the diversion works are now as follows:            Approximately 350 metal brackets (stations) were installed
            - The Sykia Dam and the namesake Hydroelectric Plant     inside  the  tunnels,  soundly  embedded  and  checked
                                                                     before the angle measurements started in order to
            - The 17.5 km long Acheloos River Diversion Tunnel with intake   eliminate any errors or failures due to incorrect installation.
            at the Sykia Reservoir
                                                                     These stations considered also as the peaks of the new
            - The Hydroelectric Plant of Pefkofyto at the exit of the diversion   Trigonometric Network, and were placed at every 100 and
            tunnel                                                   every 200 meters on both sides of the tunnels where the
                                                                     tunnel alignment was straight line, and more densely in
            - The Reregulating Reservoir of Mavromati.               curved alignment parts. Particularly regarding the entrance
            2. AIM OF PROJECT:                                       from Argithea, for approximately 1.5 km the bases were
            The project’s primary aim was the irrigation and the increase   more closely installed due to the existence of many curves
            of agricultural production and by extension of water supply to   and angles in order to achieve visibility between peaks.
            housing complexes - improvement of the quality of the water of   Approximately 2800 x 6 measurements were carried out
            River Pineios and the generation of energy.              from all brackets (stations) towards back and front aiming
                                                                     to at least 7 prisms placed on an equal number of bases,
            3. OUR CONTRIBUTION TO THE PROJECT:                      depending on visibility. Three routings were made, the first
            Establishment of surface - underground horizontal and    from the entrance of the Drakotrypa to Argithea tunnel, the
            levelling network inside and outside the open tunnels, as   second from the entrance of the Petroto to Argithea tunnel,
            well as the compilation of tunnel cross-sections.        and the third from the entrance of the Anthiro to Argithea
                                                                     tunnel for 1.5km and then it diverted left to the Argithea –
            The tunnel’s excavation works were performed from both fronts   Petroto front and on the right to the Argithea – Drakotrypa
            (Drakotrypa and Petroto) using a Tunnel Boring Machine (TBM)   front.
            and conventional excavation method. An access gallery of
            aprox. 2 km in length began at the village Anthiro and ended at   •   Externally
            the main tunnel (Drakotrypa-Petroto) forming a “T”. This created   With regard to the horizontal network outside the tunnels,
            3 tunnels as depicted below.                             both the new base plates that were created and those
            Taking into account that the tunnel construction requires   that pre-existed used as survey points 11 single & double
            specialized survey support through all its stages, our contribution   frequency GPS geodetic receivers, taking measurements
            was crucial for its smooth development and for reaching the   simultaneously.
            set aim, pertaining to the entire length of the Diversion Tunnel  - Elevation Network:
            of the Acheloos River. Essentially, our main responsibility was
            to depict the data necessary to achieve accurate joining of   The elevation network was tied to two fixed points with known
            the 2 tunnels constructed, between Drakotrypa-Argithea and   elevation (reperes) located near the entrances of each tunnel.
            Petroto-Arghithea, by using accurate information in 3D form   Surface and underground levelling was carried out.
            (horizontal and level) .                             •   Internally
            Our responsibilities did not end there. After succeeding in the   With regard to levelling inside the tunnels,  there were
            correct joining of the tunnels, and before supporting the final   loops at every 500 meters, which included the fixed metal
            tunnel with gunite , a complete survey of its condition was carried   bracketsstations, thus determining their accurate elevation.
            out, using laser scanner method in order to compile cross
            sections and calculate the quantity of concrete, membranes,



             6