Page 7 - Tunneling
P. 7

www.moniterra.engineering                                                                    TUNNELING

       •   Externally                                       •   During the installation of the metal brackets on one side
                                                                of the tunnels, there were metal pipes that impeded the
           To unify the elevation networks of the tunnels, due to   correct selection of the installation point that would meet
           their great elevation  differences, the method  of  Special   the requirement of visibility with the other bases.
           Trigonometric Levelling was used.
                                                            •   The methane fumes inside the tunnels and the landslide
       •   Complete survey of tunnels with laser scanning and
          compilation of cross-sections.                        problems due to water erosion were some of the other
                                                                problems presented  and  dealt  with  by observing  the
       After the establishment of the Trigonometrical Network and the   necessary security measures, such as special masks,
       breakthrough, the joined tunnel was scanned, using Amberg   protective helmets, etc.
       Profiler 5003 laser scanner.
                                                            5. COMPLETION TIMES
       The following methodology was used:
                                                            The following survey crews were employed:
       At each scan, targets were placed in the front and in the back of
       the Laser Scanner, which were thus located inside the scanning   •   OOne six-member crew undertook the measurements
       field  and  were  part  of  the  survey.  The  same  targets  were   of the horizontal network at the 11km long Drakotrypa to
       surveyed at the same time by the S6 Trimble total station, which   Argithea tunnel, which were completed in three days.
       was installed on a fixed metal bracket with known coordinates.  •   Another crew of two people undertook the levelling
       This meant that the specific targets were oriented based on   measurements of the levelling network, which were
       the new trigonometrical network, and with them all the imaging   completed in three days.
       points were oriented through the scanning. This procedure was   •   The five-member crew that worked for the horizontal and
       repeated at every 20 meters to allow the best possible and   levelling network at the Petroto to Argithea tunnel required
       more detailed surveying and supporti of the necessary overlap   two days, covering 3 km.
       of the consecutive scans.
                                                            •   The five-member crew that worked for the horizontal and
       For the process the data from the digital scans, we used   levelling network at the access gallery required three days
       the  Cyclon  software  by  Leica.  This  software  carried  out  the   for 2km + 4km in the main tunnel.
       registration, to allow the correct georeferencing of the surveyed
       sections in space. Based on this surveying and the axis of the  •   Three persons were needed for the special trigonometric
       tunnels, cross-sections were produced every 6.67 meters   levelling, which was completed in one day.
       except for a 2,061-meter section of the Petroto-Argithea tunnel,   •   The complete imaging of the total length of the final tunnel
       where sections produced every 9 meters.                  with the digital scanning method required approximately
       4. THE PROBLEMS PRESENTED                                fifteen days to complete by a survey crew of three.
       •   The basic problem dealt with was the constant workflow  •   It should be noted that for the surface measurements of the
          within  the  tunnels  on  a  24-hour  basis,  which  therefore   horizontal network with GPS geodetic receivers eight hours
          required the organization and installation of the survey   were needed and four people were employed.
          works when no workers or machinery would be inside the   6. EQUIPMENT USED:
          tunnels. Thus, the time when the works were carried out
          was holidays and days of leave of the permanent staff.  •   Geodetic  Stations  LEICA  1201,  1’’,+/-  (2mm+2ppm)  ,
                                                                LEICA 2003, 0,5’’, +/- (1mm+1ppm) , and Trimble S6 High
       •   The tunnels were very narrow aprox. 4.5m – 5.0m, so the   Precision, 1’’, +/- (1mm+1ppm).
          geometry of the network was not the appropriate one.
                                                            •   2 Digital Levels TRIMBLE Dini (0,3mm/km)
       •   Due to rock mass collapse in the past, access gallery
          alignment had very close and narrow curves. So in many  •   Laser Scanner 5003 AMBERG
          cases the network’s side length didn’t exceeded 15m. This   •   4 dual frequency GPS TRIMBLE R8 and 7 single frequency
          was a very dangerous situation, because an 18km tunnel   TRIMBLE R3.
          breakthrough depended on 15m measurements.
       •   Huge amounts of water were entering the tunnel from
          all sides, so measurements were taken through water
          curtains.
       •   Along the length of the Drakotrypa to Argithea tunnel rails
          were installed, which served to transport staff and materials.
          These rails were covered on their greater part by water and
          mud and thus work in this section required special attention
          during the levelling and total station’s measurements. The
          digital scan survey at this section was carried out with the
          use  of  a  special  wagon  where  the  Laser  Scanner  was
          mounted.                                                                           Ag. Stefanos tunnels





                                                                                                            7
   2   3   4   5   6   7   8