Significant Projects completed

                   1.  Completed:
                          a.  Austin ISD: Pickle Elementary School Renovation
                          b.  Austin ISD: Lively Middle School Renovation
                          c.  Austin ISD: Navarro High School Renovation

                   2.  On-going Development / Construction:



















                          a.  St. Austin Catholic School - St. Austin’s school is currently in construction and the floor
                              have been framed. FGMA’s primary responsibility is the $32M Parish and School
                              building, a 5-story structure with a rooftop playground. The program includes twenty-four
                              classrooms, a gym and locker rooms and open, collaborative learning areas throughout
                              the school. Despite several pauses along the way, the project is now in construction, with
                              a targeted occupancy date in July 2023.
                          b.  St. Theresa Catholic School - The Elmer Hall project was bid out and came in over
                              budget.  The project did not proceed into construction phase. Work on the campus
                              masterplan is currently on-going and is anticipated to include a significant addition and
                              renovation.  The project should proceed into Schematic Design and it is anticipated that
                              a portion of Elmer Hall would be included with this project.