Tata Kelola Perusahaan Tanggung Jawab Sosial Perusahaan
Good Corporate Governance Corporate Social Responsibility
Tahun 2025. Pembangunan SPAM Buaran III dilakukan melalui The construction of SPAM Buaran III is carried out through
kerja sama skema Bundling. Hingga akhir Desember 2024, Bundling scheme collaboration. At of the end of December
kemajuan konstruksi IPA Buaran III adalah sebesar 90,99%. 2024, the construction progress of IPA Buaran III was 90.99%.
4. SPAM Pesanggrahan 4. SPAM Pesanggrahan
SPAM Pesanggrahan direncanakan akan menambah supply SPAM Pesanggrahan is planned to increase supply by 750 liters
sebesar 750 lps. Pembangunan IPA Pesanggrahan dilakukan per second. The construction of Pesanggrahan IPA is carried
oleh PAM JAYA. Di tahun 2024, kemajuan pembangunan SPAM out by PAM JAYA. In 2024, the progress of SPAM Pesanggrahan
Pesanggrahan adalah sebesar 48,62%. construction was 48.62%.
5. SPAM Ciliwung 5. SPAM Ciliwung
Pembangunan SPAM Ciliwung direncanakan akan menambah The construction of SPAM Ciliwung is planned to increase
supply sebesar 200 lps. Pembangunan IPA Ciliwung akan dilakukan supply by 200 liters per second. The construction of Ciliwung
oleh PAM JAYA. Di tahun 2024, kemajuan SPAM Ciliwung sampai IPA will be carried out by PAM JAYA. In 2024, the progress of
dengan akhir tahun 2024, yaitu telah dilakukan kick off project SPAM Ciliwung until the end of 2024 included the kick off of the
IPA Ciliwung pada tanggal 25 November 2024 dengan progres Ciliwung IPA project on November 25, 2024 with work progress
pekerjaan sampai dengan akhir 2024 adalah sebesar 0,36%. until the end of 2024 being 0.36%.
6. Reservoir Komunal (RK) 6. Communal Reservoir (RK)
PAM JAYA juga membangun Reservoir Komunal sebagai bentuk As part of its innovation efforts in SPAM development, PAM JAYA
inovasi pengembangan SPAM. Reservoir Komunal merupakan also constructs Communal Reservoirs that serve as infrastructure
infrastruktur untuk mengatur dan meningkatkan tekanan pada to regulate and increase pressure in areas far from the IPA and
daerah terjauh dari IPA dan pompa booster yang areanya booster pumps in low-pressure areas.
bertekanan rendah.
Manfaat pembangunan Reservoir Komunal di antaranya: The benefits of building Communal Reservoirs include:
a. ● Menjadi penampungan air sementara untuk area yang a. ● Acting as a temporary water storage for low-pressure areas;
bertekanan rendah;
b. ● Menjaga optimalisasi supply di area bertekanan rendah; b. ● Ensuring optimal supply in low-pressure areas;
c. ● Pelanggan yang tidak memiliki penampungan air tetap c. ● Customers who do not have water reservoirs still get supply
mendapatkan supply dari Reservoir Komunal; from the Communal Reservoir;
d. ● Berdampak kepada peningkatan supply pelanggan existing d. ● Contributing to increased supply for existing customers
dan untuk pelayanan potential new customers; and potential new customers;
e. ● Membantu menjaga konservasi lingkungan. e. ● Supporting environmental conservation efforts.
Sampai dengan akhir Tahun 2024, PAM JAYA telah membangun 7 By the end of 2024, PAM JAYA constructed 7 communal
reservoir komunal, yaitu Reservoir Komunal Duri Kosambi, Tamansari, reservoirs, namely RK Duri Kosambi, Tamansari, Pluit Reservoir,
Waduk Pluit, Cilincing, Marunda, Gandaria Utara, Tambora. Cilincing, Marunda, Gandaria Utara, and Tambora.
7. Penurunan Non-Revenue Water (NRW) 7. Decreasing Non-Revenue Water (NRW)
PAM JAYA telah melakukan Studi Pendahuluan NRW di wilayah PAM JAYA has conducted a Preliminary Study of NRW in the
DKI Jakarta yang bertujuan untuk pemetaan kondisi NRW dan DKI Jakarta area aimed at mapping the NRW conditions and
penyusunan roadmap NRW untuk mencapai target NRW 30% developing an NRW roadmap to achieve a 30% NRW target
di tahun 2030. by 2030.
Di tahap awal, PAM JAYA melakukan program penurunan NRW In the initial stage, PAM JAYA initiated NRW reduction programs in
pada 6 (enam) DMA Pilot Project yang tersebar di area Barat 6 (six) DMA Pilot Projects spread across the Western and Eastern
dan Timur wilayah pelayanan. DMA Pilot Project tersebut di service areas. These DMA Pilot Projects are located in:
antaranya berada di area:
a. ● 15802 Kampung Melayu (Wilayah Timur) a. ● 15802 Kampung Melayu (East Area)
b. ● 14704 Duren Sawit (Wilayah Timur) b. ● 14704 Duren Sawit (East Area)
c. ● 04902 Pulomas (Wilayah Timur) c. ● 04902 Pulomas (East Area)
d. ● S012 Asem Baris (Wilayah Barat) d. ● S012 Asem Baris (West Area)
e. ● B004 Kebon Jeruk (Wilayah Barat) e. ● B004 Kebon Jeruk (West Area)
f. ● B014 Abdul Wahab (Wilayah Barat) f. ● B014 Abdul Wahab (West Area)