4








                                                                     2 ND         TECHNOLOGY

                 DEVELOPMENT AND APPLICATION                                    DEVELOPMENT

           OF 4D PROCESS SIMULATION SYSTEM                                                    ISSUES





                          Construction Simulation of Culvert Passing through Railway
          Front jacking method was introduced to install culvert that pass through the lower section of the existing
               railway ( KTX ) and to enter industrial sites. For this, temporary facilities are developed with BIM and
    implemented with 4D simulation to be utilized as decision-making data on design review and construction order.

                 3D Information Modeling and 4D Simulation of Facilities for Mineral
                                                                           Resources Distribution
        A port railway was planned to transport minerals from mines located in Roy Hill, Australia, to adjacent ports.
          We conducted BIM and 4D simulation for plant facilities, which are for collecting, loading and transporting
     minerals, also the facilities for loading ships. Those data were utilized in reviewing designs and decision-making.

                                          Water Inflow Pipeline Construction ( Asan DC2 )
      About the underground pipeline system entering the industrial complex, process management was carried out
      by establishing BIM and implementing it with 4D simulation. As a result, the construction quality was increased
            during the construction and it has been used for maintenance after the completion of the construction.